United States › Grid › Interconnection queues › Pennsylvania

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Pennsylvania — page 20

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,354164.3 GW
Active in queue12.5 GW231 requests
Agreement signed2,306 MW58 requests
Withdrawn1,354164.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,354 requests · page 20 of 28
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project A20, Dauphin County
Gas
12.0 MWWithdrawn / abandoned Dauphin, PAPJM Jul 1998
Solar project AH1-207, Fayette County
Solar
12.0 MWWithdrawn / abandoned Fayette, PAPJM Sep 2021target 2024
Solar project AH1-208, Fayette County
Solar
12.0 MWWithdrawn / abandoned Fayette, PAPJM Sep 2021target 2024
Battery storage project AH1-632, Franklin County
Battery storage
12.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2021target 2023
Gas project AC1-183, Berks County
Gas
12.0 MWWithdrawn / abandoned Berks, PAPJM Oct 2016target 2019
Magenta Solar
Solar
12.0 MWWithdrawn / abandoned Bedford, PAPJM Feb 2020target 2026
Solar project W3-169, Adams County
Solar
12.0 MWWithdrawn / abandoned Adams, PAPJM Oct 2010target 2012
Salt Solar
Solar
12.0 MWWithdrawn / abandoned Bedford, PAPJM Jun 2020target 2026
Gas project W4-051, Philadelphia County
Gas
12.0 MWWithdrawn / abandoned Philadelphia, PAPJM Jan 2011target 2011
Hydro project U1-076, Allegheny County
Hydro
12.0 MWWithdrawn / abandoned Allegheny, PAPJM Apr 2008target 2015
Battery storage project AF1-295, Perry County
Battery storage
12.0 MWWithdrawn / abandoned Perry, PAPJM Sep 2019target 2022
Gas project AD2-109, Fayette County
Gas
12.0 MWWithdrawn / abandoned Fayette, PAPJM Mar 2018target 2022
Solar project AH1-209, Fayette County
Solar
12.0 MWWithdrawn / abandoned Fayette, PAPJM Sep 2021target 2024
Solar project AH1-210, Fayette County
Solar
12.0 MWWithdrawn / abandoned Fayette, PAPJM Sep 2021target 2024
Solar project AH1-200, Wyoming County
Solar
12.0 MWWithdrawn / abandoned Wyoming, PAPJM Sep 2021target 2023
Solar project AH1-211, Fayette County
Solar
12.0 MWWithdrawn / abandoned Fayette, PAPJM Sep 2021target 2024
Emsworth Back Channel Dam Hydroelectric Project
Hydro
12.0 MWWithdrawn / abandoned Allegheny, PAPJM Mar 2020target 2024
Fayetteville Solar
Solar
11.9 MWWithdrawn / abandoned Franklin, PAPJM Sep 2019target 2022
Other project U2-085, Lancaster County
Other
11.4 MWWithdrawn / abandoned Lancaster, PAPJM Jul 2008target 2009
Other project AE2-009, Adams County
Other
11.0 MWWithdrawn / abandoned Adams, PAPJM Oct 2018target 2020
United Corrstack
Other
11.0 MWWithdrawn / abandoned Berks, PAPJM Jul 2004target 2006
Ce-Jacksonville
Solar
10.6 MWWithdrawn / abandoned Centre, PAPJM Mar 2019target 2023
Solar project AH1-394, Tioga County
Solar
10.5 MWWithdrawn / abandoned Tioga, PAPJM Sep 2021target 2023
Solar project AG2-554, Centre County
Solar
10.0 MWWithdrawn / abandoned Centre, PAPJM Mar 2021target 2023
Solar + storage project AI1-193, Adams County
Solar + storage
10.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2022target 2024
Solar project AG1-201, Mercer County
Solar
10.0 MWWithdrawn / abandoned Mercer, PAPJM Sep 2020target 2022
Solar + storage project AI1-144, Adams County
Solar + storage
10.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2022target 2024
Ponytail Solar
Solar
10.0 MWWithdrawn / abandoned Armstrong, PAPJM Mar 2020target 2023
Solar project AH1-494, Lancaster County
Solar
10.0 MWWithdrawn / abandoned Lancaster, PAPJM Sep 2021target 2024
Solar project AH1-445, Mifflin County
Solar
10.0 MWWithdrawn / abandoned Mifflin, PAPJM Sep 2021target 2023
PA SP
Solar
10.0 MWWithdrawn / abandoned Carbon, PAPJM Sep 2009target 2016
Solar project AG1-296, Jefferson County
Solar
10.0 MWWithdrawn / abandoned Jefferson, PAPJM Sep 2020target 2022
Grows North LF
Other
10.0 MWWithdrawn / abandoned Bucks, PAPJM Jul 2008target 2011
Solar project AH1-495, Snyder County
Solar
10.0 MWWithdrawn / abandoned Snyder, PAPJM Sep 2021target 2024
Chambersburg Energy
Battery storage
10.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2020target 2027
Solar project AG2-089, Westmoreland County
Solar
10.0 MWWithdrawn / abandoned Westmoreland, PAPJM Jan 2021target 2022
Solar project AG1-241, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, PAPJM Sep 2020target 2022
Solar project AE1-182, Cumberland County
Solar
10.0 MWWithdrawn / abandoned Cumberland, PAPJM Sep 2018
Solar project AH2-356, Jefferson County
Solar
10.0 MWWithdrawn / abandoned Jefferson, PAPJM Mar 2022target 2024
Solar project AI1-164, Venango County
Solar
10.0 MWWithdrawn / abandoned Venango, PAPJM Sep 2022target 2026
Gans Energy CT and BESS
Battery storage
10.0 MWWithdrawn / abandoned Fayette, PAPJM Sep 2020target 2027
Hydro project U1-082, Fayette County
Hydro
10.0 MWWithdrawn / abandoned Fayette, PAPJM Apr 2008target 2015
Solar project AG2-398, Lycoming County
Solar
10.0 MWWithdrawn / abandoned Lycoming, PAPJM Mar 2021target 2023
Hydro project U1-081, Westmoreland County
Hydro
10.0 MWWithdrawn / abandoned Westmoreland, PAPJM Apr 2008target 2015
Gas project G48, Berks County
Gas
10.0 MWWithdrawn / abandoned Berks, PAPJM Jul 2001target 2003
Solar project AG1-243, Franklin County
Solar
10.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2020target 2022
Solar project AG2-334, Huntingdon County
Solar
10.0 MWWithdrawn / abandoned Huntingdon, PAPJM Mar 2021target 2023
Elm Line Energy Storage
Battery storage
10.0 MWWithdrawn / abandoned Bradford, PAPJM Mar 2020target 2021
Solar project AG2-651, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, PAPJM Mar 2021target 2023
Solar project AG2-371, Cumberland County
Solar
10.0 MWWithdrawn / abandoned Cumberland, PAPJM Mar 2021target 2023
Page 20 of 28

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)