πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

SOLAR Β· PJM

Solar project AH2-356, Jefferson County

Solar project AH2-356, Jefferson County is a 10.0 MW solar request withdrawn in the PJM interconnection queue, in Jefferson County, Pennsylvania, connecting to PENELEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedSep 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH2-356
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Brookeville 34.5 kV
Location
Jefferson County, Pennsylvania
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 March 2022
Proposed online date
December 2024
Withdrawn
September 2023

Location

Marker shows the centre of Jefferson County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Jefferson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem