SOLAR Β· PJM

Solar project AG1-201, Mercer County

Solar project AG1-201, Mercer County is a 10.0 MW solar request withdrawn in the PJM interconnection queue, in Mercer County, Pennsylvania, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2020 (completed)
  2. Withdrawn / abandonedNov 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG1-201
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Hadley 12.47 kV
Location
Mercer County, Pennsylvania
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
22 September 2020
Proposed online date
December 2022
Withdrawn
November 2020

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.