🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Pennsylvania

HYDRO · PJM

Emsworth Back Channel Dam Hydroelectric Project

Emsworth Back Channel Dam Hydroelectric Project is a 12.0 MW hydro request withdrawn in the PJM interconnection queue, in Allegheny County, Pennsylvania, connecting to DL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2020 (completed)
  2. Withdrawn / abandonedFeb 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AF2-367
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DL
Connection point (POI)
Neville 23 kV
Location
Allegheny County, Pennsylvania
Technology
Hydro: 12.0 MW
Total requested
12.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Withdrawn
Entered queue
31 March 2020
Proposed online date
December 2024
Withdrawn
February 2025

Location

Marker shows the centre of Allegheny County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Allegheny County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem