United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
SOLAR Β· PJMSolar project AH1-494, Lancaster County
Solar project AH1-494, Lancaster County is a 10.0 MW solar request withdrawn in the PJM interconnection queue, in Lancaster County, Pennsylvania, connecting to PPL.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandonedSep 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-494
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- Wakefield 12 kV
- Location
- Lancaster County, Pennsylvania
- Technology
- Solar: 10.0 MW
- Total requested
- 10.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 10 September 2021
- Proposed online date
- June 2024
- Withdrawn
- September 2023
Location
Marker shows the centre of Lancaster County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Lancaster County
- HoltwoodHydro Β· 140 MW Β· built
- HoltwoodHydro Β· 107 MW Β· built
- Dart ContainerOther Β· 11.4 MW Β· built
- YorkGas Β· 10.0 MW Β· built
- Keystone SolarSolar Β· 5.0 MW Β· built
- Turkey Hill Dairy WFOnshore wind Β· 3.2 MW Β· built
- HoltwoodHydro Β· 2.0 MW Β· built
- Granger of HoneybrookOther Β· 1.6 MW Β· built
- Sight and Sound TheaterGas Β· 1.6 MW Β· built
- ElizabethtownGas Β· 0.3 MW Β· built
- Gas project AA2-109, Lancaster CountyGas Β· 1,100 MW Β· withdrawn
- Gas project U1-016, Lancaster CountyGas Β· 700 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem