🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 2 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Atlantic Shores Offshore Wind Bight 5
Offshore wind · Atlantic Shores Offshore Wind Bight, LLC
2,100 MWWithdrawn / abandoned Richmond, NYNYISO Feb 2022
Atlantic Shores Offshore Wind Bight 4
Offshore wind · Atlantic Shores Offshore Wind Bight, LLC
2,100 MWWithdrawn / abandoned Kings, NYNYISO Feb 2022
Atlantic Shores Offshore Wind Bight 1
Offshore wind · Atlantic Shores Offshore Wind Bight, LLC
2,100 MWWithdrawn / abandoned Kings, NYNYISO Feb 2022
Atlantic Shores Offshore Wind Bight 3
Offshore wind · Atlantic Shores Offshore Wind Bight, LLC
2,100 MWWithdrawn / abandoned Suffolk, NYNYISO Feb 2022
Atlas
Solar + storage
2,074 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2022
Ashton Energy Center
Solar + storage
2,049 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2032
BlueWater Solar
Solar + storage
2,031 MWWithdrawn / abandoned La Paz, AZCAISO Apr 2023target 2028
Cobisa-Greenville
Battery storage · Cobisa
2,023 MWWithdrawn / abandoned ERCOT Jul 2002target 2017
Gemini Wind North
Onshore wind
2,006 MWWithdrawn / abandoned CACAISO Apr 2018target 2025
Other project PQ0002, Cerro Gordo County
Other
2,000 MWWithdrawn / abandoned Cerro Gordo, IAMISO Aug 2015target 2021
Onshore wind project G903, Wright County
Onshore wind
2,000 MWWithdrawn / abandoned Wright, MNMISO Oct 2007target 2010
Onshore wind project GI-0612, Hand County
Onshore wind
2,000 MWWithdrawn / abandoned Hand, SDWest Aug 2006target 2009
Solar + storage project Q109, Navajo County
Solar + storage
2,000 MWWithdrawn / abandoned Navajo, AZWest Jul 2023target 2027
Empire Connection DC
Other · Conjunction, LLC
2,000 MWWithdrawn / abandoned NYNYISO Jun 2003
Onshore wind project G705, Hand County
Onshore wind
2,000 MWWithdrawn / abandoned Hand, SDMISO Nov 2006target 2009
Solar + storage project Q33, Pinal County
Solar + storage
2,000 MWWithdrawn / abandoned Pinal, AZWest Oct 2023target 2028
Coal project R68, Jefferson County
Coal
1,940 MWWithdrawn / abandoned Jefferson, OHPJM Jan 2007target 1980
Gas project IC-242, Putnam County
Gas
1,922 MWWithdrawn / abandoned Putnam, GASoutheast Aug 2010
Gas project IC-244, Hancock County
Gas
1,918 MWWithdrawn / abandoned Hancock, GASoutheast Aug 2010
Alamitos Energy Center
Gas
1,903 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2012target 2025
Onshore wind project GEN-2024-130, Tulsa County
Onshore wind
1,900 MWWithdrawn / abandoned Tulsa, OKSPP Mar 2025target 2031
Vinson Energy
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2027
Nimitz 2 Generation
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2026
Intrepid Energy
Wind + storage
1,887 MWWithdrawn / abandoned Humboldt, CACAISO Apr 2020target 2027
Nimitz 1 Generation
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2024
Tempest Generation
Wind + storage
1,887 MWWithdrawn / abandoned Humboldt, CACAISO Apr 2019target 2025
Seawolf Generation
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2024
Ethan Creek
Onshore wind
1,870 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Coal project I07, Jefferson County
Coal
1,860 MWWithdrawn / abandoned Jefferson, OHPJM Apr 2002target 2005
Other project 136, Hawkins County
Other
1,820 MWWithdrawn / abandoned Hawkins, TNSoutheast Nov 2000
Other project 135, Hawkins County
Other
1,820 MWWithdrawn / abandoned Hawkins, TNSoutheast Nov 2000
Other project 188, Hawkins County
Other
1,820 MWWithdrawn / abandoned Hawkins, TNSoutheast Feb 2002
Gas project L01, Charles County
Gas
1,800 MWWithdrawn / abandoned Charles, MDPJM Aug 2003target 2008
Gas project M01, Charles County
Gas
1,800 MWWithdrawn / abandoned Charles, MDPJM Feb 2004target 2008
Solar + storage project G0698, Crook County
Solar + storage
1,800 MWWithdrawn / abandoned Crook, ORWest Sep 2021target 2025
Porthos Solar
Solar + storage
1,800 MWWithdrawn / abandoned Riverside, CACAISO Apr 2018target 2022
Gas project IC-050, Talladega County
Gas
1,800 MWWithdrawn / abandoned Talladega, ALSoutheast
Gas project K08, Charles County
Gas
1,800 MWWithdrawn / abandoned Charles, MDPJM May 2003
Battery storage project C2-19, Kootenai County
Battery storage · PacifiCorp
1,800 MWWithdrawn / abandoned Kootenai, IDWest Apr 2022target 2028
Chance Solar
Solar + storage
1,790 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2028
Other project J4176
Other
1,750 MWWithdrawn / abandoned MISO target 2028
Hatfield Ferry, Units 1, 2, and 3
Coal
1,710 MWWithdrawn / abandoned Greene, PAPJM Oct 2014target 2019
Battery storage project Q400, Coconino County
Battery storage
1,700 MWWithdrawn / abandoned Coconino, AZWest Sep 2021target 2023
Cowboy Mesa Wind
Onshore wind
1,700 MWWithdrawn / abandoned Lincoln, NMCAISO Mar 2011target 2016
Gas project AH1-674, Beaver County
Gas · Shippingport Power Station, LLC
1,700 MWWithdrawn / abandoned Beaver, PAPJM target 2028
Battery storage project 566988, Oconee County
Battery storage
1,680 MWWithdrawn / abandoned Oconee, SCSoutheast Jun 2022
Lava Ridge Wind
Wind + storage
1,666 MWWithdrawn / abandoned Lincoln, IDCAISO Apr 2021target 2025
Nine Mile Point Station Unit #3
Nuclear · UniStar Nuclear Energy
1,660 MWWithdrawn / abandoned Oswego, NYNYISO Feb 2008
Nuclear project G733, Callaway County
Nuclear
1,650 MWWithdrawn / abandoned Callaway, MOMISO Feb 2007target 2009
Solar + storage project Q469, Pinal County
Solar + storage
1,650 MWWithdrawn / abandoned Pinal, AZWest Mar 2022target 2025
Page 2 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)