United States › Grid › Interconnection queues › Texas
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in Texas (2022 requests) — page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Crossroads Wind Onshore wind · HyFuels Green Lake Wind LLC |
277 MW | Agreement signed |
| Mystic Springs Renewable Energy Solar SLF Solar + storage · Mystic Spring Renewable Energy LLC |
259 MW | Agreement signed |
| Drake BESS Battery storage · Mallard Energy Storage LLC |
257 MW | Agreement signed |
| Masava Storage Battery storage · Savannah Oaks Solar Project, LLC |
257 MW | In study |
| Shepard Energy Storage Battery storage · Shepard Energy Storage LLC |
257 MW | Agreement signed |
| SanPat Solar II Solar · CGRP 04, LLC |
256 MW | Agreement signed |
| Bayside 2 BESS Battery storage |
252 MW | Paused / redesign |
| Cibeles Solar Solar · Elawan Cibeles Solar, LLC |
252 MW | Agreement signed |
| Buzios Solar Solar + storage · Roaring Springs Solar, LLC |
252 MW | Agreement signed |
| August Draw Solar Solar · August Draw Solar Holdings, LLC |
250 MW | Agreement signed |
| Best Southwest BESS Battery storage |
241 MW | Paused / redesign |
| Bracero Pecan Storage Battery storage · Bracero Pecan Storage LLC |
238 MW | Agreement signed |
| Bora Bora Solar Solar |
233 MW | Paused / redesign |
| Petunia Storage Project Battery storage · Petunia Storage Project LLC |
232 MW | In study |
| Taormina Storage Battery storage · Taormina Storage Project LLC |
232 MW | Agreement signed |
| Adelite Storage Battery storage · Adelite Storage Project LLC |
232 MW | Agreement signed |
| Lavender Storage Project Battery storage · Lavender Storage Project LLC |
232 MW | Agreement signed |
| Rubicon Echo Wind Onshore wind |
228 MW | Paused / redesign |
| White Tail Solar Solar · Mule Deer Solar LLC |
227 MW | In study |
| Dunkel BESS Battery storage · Momentum Energy Storage Partners |
226 MW | In study |
| Diver Solar Solar · Diver Solar |
226 MW | Agreement signed |
| Rubicon Alpha Wind Onshore wind · Throckmorton Wind, LLC |
226 MW | Agreement signed |
| Olympic BESS Battery storage · SMT Olympic BESS LLC |
223 MW | In study |
| Shoshana Storage Battery storage · Shoshana Storage Project LLC |
221 MW | In study |
| Sepanta Solar Solar · BREG - Belgian Renewable Energy Group |
217 MW | In study |
| Puerto Del Sol 2 Solar · PUERTO DEL SOL, LLC |
214 MW | In study |
| Puerto Del Sol 1 Solar · PUERTO DEL SOL, LLC |
214 MW | In study |
| Rockridge Solar Solar · Magnolia Solar Development LLC |
211 MW | Agreement signed |
| Bessie Storage Battery storage · Bessie Energy Storage, LLC |
211 MW | In study |
| Cumulus Grid BESS Battery storage · Cumulus Grid, LLC |
211 MW | Agreement signed |
| Leon Solar Park Solar + storage · Misae Solar IV LLC |
210 MW | Agreement signed |
| Forts Trail BESS Solar + storage · JC Central Bluff, LLC |
209 MW | In study |
| Anatole Renewable Energy Storage Battery storage · Eustace Storage LLC |
208 MW | Agreement signed |
| Longfellow Solar II Solar + storage · CENTURY GAS PROCESSING, LLC |
207 MW | Agreement signed |
| Pintail Pass BESS Battery storage · Pintail Pass BESS, LLC |
207 MW | Agreement signed |
| St. Gall Solar Solar · St. Gall Solar LLC |
207 MW | In study |
| Rock N' Roll Storage Two Solar + storage · Rock N‚Äô Roll Solar, LLC |
206 MW | In study |
| Rhapsody Storage Battery storage · Destiny Storage, LLC |
206 MW | Agreement signed |
| Soda Lake BESS 2 SLF Solar + storage · Crane II Solar Electric, LLC |
205 MW | In study |
| Citrus Grove Energy Storage Battery storage |
205 MW | Paused / redesign |
| Sahara II BESS (Soho II BESS) Battery storage · ESTX-PLD-HOUSTON2 |
204 MW | Agreement signed |
| Urca Solar Solar |
204 MW | Paused / redesign |
| Hoskins Solar Solar · SGT HOSKINS SOLAR PROJECT, LLC |
204 MW | In study |
| Stockdale BESS Battery storage |
204 MW | Paused / redesign |
| Utica BESS Battery storage |
204 MW | Paused / redesign |
| Soda Lake BESS 1 Battery storage · Mendoza Trail BESS, LLC |
204 MW | Agreement signed |
| Cornwall BESS Battery storage |
204 MW | Paused / redesign |
| Sierra Diablo Energy Storage Battery storage · SIERRA DIABLO ENERGY STORAGE LLC |
204 MW | In study |
| Sultan BESS Battery storage |
204 MW | Paused / redesign |
| Black & Gold Energy Storage Battery storage · Black & Gold Energy Storage, LLC |
204 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)283 · 56.6 GW
- MISO (Midcontinent)6 · 1,095 MW
- SPP (Southwest Power Pool)2 · 693 MW
- West (non-ISO utilities)2 · 150 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)