United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Texas (2022 requests) — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown29358.6 GW
Active in queue58.6 GW293 requests
Agreement signed23.9 GW116 requests
Withdrawn8117.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

293 requests · page 2 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Crossroads Wind
Onshore wind · HyFuels Green Lake Wind LLC
277 MWAgreement signed Victoria, TXERCOT Sep 2022target 2027
Mystic Springs Renewable Energy Solar SLF
Solar + storage · Mystic Spring Renewable Energy LLC
259 MWAgreement signed Kaufman, TXERCOT May 2022target 2028
Drake BESS
Battery storage · Mallard Energy Storage LLC
257 MWAgreement signed Collin, TXERCOT Jun 2022target 2026
Masava Storage
Battery storage · Savannah Oaks Solar Project, LLC
257 MWIn study Madison, TXERCOT Sep 2022target 2028
Shepard Energy Storage
Battery storage · Shepard Energy Storage LLC
257 MWAgreement signed Galveston, TXERCOT Dec 2022target 2027
SanPat Solar II
Solar · CGRP 04, LLC
256 MWAgreement signed San Patricio, TXERCOT Feb 2022target 2027
Bayside 2 BESS
Battery storage
252 MWPaused / redesign Dewitt, TXERCOT Mar 2022
Cibeles Solar
Solar · Elawan Cibeles Solar, LLC
252 MWAgreement signed Mclennan, TXERCOT May 2022target 2027
Buzios Solar
Solar + storage · Roaring Springs Solar, LLC
252 MWAgreement signed Motley, TXERCOT Sep 2022target 2026
August Draw Solar
Solar · August Draw Solar Holdings, LLC
250 MWAgreement signed Reeves, TXERCOT Sep 2022target 2028
Best Southwest BESS
Battery storage
241 MWPaused / redesign Dallas, TXERCOT May 2022target 2025
Bracero Pecan Storage
Battery storage · Bracero Pecan Storage LLC
238 MWAgreement signed Reeves, TXERCOT Nov 2022target 2027
Bora Bora Solar
Solar
233 MWPaused / redesign Wichita, TXERCOT Sep 2022
Petunia Storage Project
Battery storage · Petunia Storage Project LLC
232 MWIn study Milam, TXERCOT Mar 2022target 2027
Taormina Storage
Battery storage · Taormina Storage Project LLC
232 MWAgreement signed Bexar, TXERCOT Apr 2022target 2029
Adelite Storage
Battery storage · Adelite Storage Project LLC
232 MWAgreement signed Milam, TXERCOT Jun 2022target 2027
Lavender Storage Project
Battery storage · Lavender Storage Project LLC
232 MWAgreement signed Bexar, TXERCOT Feb 2022target 2029
Rubicon Echo Wind
Onshore wind
228 MWPaused / redesign Haskell, TXERCOT May 2022
White Tail Solar
Solar · Mule Deer Solar LLC
227 MWIn study Deaf Smith, TXERCOT Feb 2022target 2027
Dunkel BESS
Battery storage · Momentum Energy Storage Partners
226 MWIn study Lubbock, TXERCOT Jun 2022target 2027
Diver Solar
Solar · Diver Solar
226 MWAgreement signed Limestone, TXERCOT Sep 2022target 2026
Rubicon Alpha Wind
Onshore wind · Throckmorton Wind, LLC
226 MWAgreement signed Haskell, TXERCOT May 2022target 2027
Olympic BESS
Battery storage · SMT Olympic BESS LLC
223 MWIn study Nueces, TXERCOT Oct 2022target 2027
Shoshana Storage
Battery storage · Shoshana Storage Project LLC
221 MWIn study Matagorda, TXERCOT Mar 2022target 2028
Sepanta Solar
Solar · BREG - Belgian Renewable Energy Group
217 MWIn study Nolan, TXERCOT Oct 2022target 2029
Puerto Del Sol 2
Solar · PUERTO DEL SOL, LLC
214 MWIn study Cameron, TXERCOT May 2022target 2027
Puerto Del Sol 1
Solar · PUERTO DEL SOL, LLC
214 MWIn study Cameron, TXERCOT May 2022target 2026
Rockridge Solar
Solar · Magnolia Solar Development LLC
211 MWAgreement signed Guadalupe, TXERCOT Apr 2022target 2027
Bessie Storage
Battery storage · Bessie Energy Storage, LLC
211 MWIn study Starr, TXERCOT Feb 2022target 2026
Cumulus Grid BESS
Battery storage · Cumulus Grid, LLC
211 MWAgreement signed Ellis, TXERCOT Mar 2022target 2028
Leon Solar Park
Solar + storage · Misae Solar IV LLC
210 MWAgreement signed Leon, TXERCOT Sep 2022target 2026
Forts Trail BESS
Solar + storage · JC Central Bluff, LLC
209 MWIn study Taylor, TXERCOT Jun 2022target 2028
Anatole Renewable Energy Storage
Battery storage · Eustace Storage LLC
208 MWAgreement signed Henderson, TXERCOT Jun 2022target 2027
Longfellow Solar II
Solar + storage · CENTURY GAS PROCESSING, LLC
207 MWAgreement signed Pecos, TXERCOT Nov 2022target 2027
Pintail Pass BESS
Battery storage · Pintail Pass BESS, LLC
207 MWAgreement signed San Patricio, TXERCOT Apr 2022target 2026
St. Gall Solar
Solar · St. Gall Solar LLC
207 MWIn study Pecos, TXERCOT Feb 2022target 2026
Rock N' Roll Storage Two
Solar + storage · Rock N‚Äô Roll Solar, LLC
206 MWIn study Brazoria, TXERCOT Feb 2022target 2027
Rhapsody Storage
Battery storage · Destiny Storage, LLC
206 MWAgreement signed Harris, TXERCOT Aug 2022target 2026
Soda Lake BESS 2 SLF
Solar + storage · Crane II Solar Electric, LLC
205 MWIn study Crane, TXERCOT Sep 2022target 2027
Citrus Grove Energy Storage
Battery storage
205 MWPaused / redesign Hidalgo, TXERCOT Nov 2022target 2026
Sahara II BESS (Soho II BESS)
Battery storage · ESTX-PLD-HOUSTON2
204 MWAgreement signed Brazoria, TXERCOT Aug 2022target 2026
Urca Solar
Solar
204 MWPaused / redesign Live Oak, TXERCOT Apr 2022
Hoskins Solar
Solar · SGT HOSKINS SOLAR PROJECT, LLC
204 MWIn study Lamar, TXERCOT Oct 2022target 2026
Stockdale BESS
Battery storage
204 MWPaused / redesign Wilson, TXERCOT Mar 2022
Utica BESS
Battery storage
204 MWPaused / redesign Guadalupe, TXERCOT Sep 2022
Soda Lake BESS 1
Battery storage · Mendoza Trail BESS, LLC
204 MWAgreement signed Crane, TXERCOT Sep 2022target 2026
Cornwall BESS
Battery storage
204 MWPaused / redesign Williamson, TXERCOT Mar 2022
Sierra Diablo Energy Storage
Battery storage · SIERRA DIABLO ENERGY STORAGE LLC
204 MWIn study Van Zandt, TXERCOT Aug 2022target 2026
Sultan BESS
Battery storage
204 MWPaused / redesign Bosque, TXERCOT Mar 2022
Black & Gold Energy Storage
Battery storage · Black & Gold Energy Storage, LLC
204 MWAgreement signed Menard, TXERCOT Jul 2022target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)