Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,486351.5 GW
Active in queue476.4 GW2,094 requests
Agreement signed124.6 GW606 requests
Withdrawn917184.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,486 requests · page 2 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Meitner 2 Wind
Onshore wind · IP Meitner, LLC
709 MWIn study Gray, TXERCOT Jun 2025target 2028
Texpo
Gas · Oklaunion Power Station, LLC
680 MWIn study Wilbarger, TXERCOT Mar 2021target 2027
Dovetail Solar 3
Solar + storage · Hecate Energy Dovetail Solar Holdings LLC
666 MWIn study Jack, TXERCOT Dec 2021target 2029
Dovetail Solar 1
Solar + storage · Hecate Energy Dovetail Solar 1 LLC
666 MWIn study Jack, TXERCOT Sep 2021target 2027
Dovetail Solar 2
Solar + storage · Hecate Energy Dovetail Solar 2 LLC
666 MWIn study Jack, TXERCOT Oct 2021target 2029
Jack County III – 345 kV
Gas · Jack County Power Development, LLC
660 MWIn study Jack, TXERCOT Nov 2023target 2027
Coleto Creek - Fuel Change Only
Gas · COLETO CREEK POWER LLC
655 MWIn study Goliad, TXERCOT Apr 2025target 2026
Commodus 2 Wind
Onshore wind · IP Blackwell II, LLC
642 MWIn study Swisher, TXERCOT Mar 2025target 2029
Commodus Wind
Onshore wind · IP Blackwell, LLC
641 MWIn study Briscoe, TXERCOT Jul 2024target 2029
Cavell Wind
Onshore wind · IP Cavell, LLC
641 MWIn study Castro, TXERCOT Jul 2024target 2029
Aurelius 3 Wind
Onshore wind · IP Roman III, LLC
623 MWIn study Deaf Smith, TXERCOT Dec 2023target 2029
Aurelius 2 Wind
Onshore wind · IP Roman Wind II, LLC
622 MWIn study Deaf Smith, TXERCOT Dec 2023target 2028
Howard Road BESS
Battery storage · Project Fast Flow LLC
618 MWIn study Bexar, TXERCOT Jul 2025target 2028
Comanche BESS
Battery storage · ENERGOS BESS
614 MWIn study Comanche, TXERCOT Dec 2024target 2028
Tumbleweed Solar
Solar + storage · Hecate Energy Tumbleweed Solar LLC
614 MWIn study Borden, TXERCOT Sep 2023target 2027
Symphony BESS
Battery storage · Symphony BESS, LLC
612 MWIn study Austin, TXERCOT Feb 2025target 2028
Skylab Solar
Solar · EDF Renewables Development, Inc.
610 MWIn study Wharton, TXERCOT Jun 2020target 2025
White Oak King Wind
Onshore wind · KSK Wind Farm 1, LLC
607 MWIn study King, TXERCOT Mar 2023target 2027
Kingsmill Wind SLF
Onshore wind · Kingsmill Wind, LLC
606 MWIn study Carson, TXERCOT Jan 2024target 2029
Lavita BESS
Battery storage · Lavita BESS, LLC
606 MWIn study Bell, TXERCOT Dec 2024target 2028
Hiru Solar
Solar + storage · Hecate Energy Hazel LLC
604 MWIn study Clay, TXERCOT Apr 2021target 2029
Moccasin Storage
Solar + storage · ENGIE IR Holdings LLC
603 MWIn study Jones, TXERCOT Jan 2025target 2028
Hobby BESS I
Battery storage · Airport Storage II LLC
603 MWIn study Harris, TXERCOT Sep 2024target 2027
Rocking X Solar
Solar · 7100 Tin Top LLC
602 MWIn study Parker, TXERCOT Oct 2023target 2027
Reunion Solar
Solar + storage · Reunion Solar, LLC
601 MWIn study Wilbarger, TXERCOT Mar 2025target 2028
Scorpius Solar
Solar · Ben Milam Solar 4
600 MWIn study Milam, TXERCOT Dec 2024target 2029
Tempesta BESS
Battery storage
600 MWPaused / redesign Kaufman, TXERCOT Jun 2022
Longleaf Power Station
Gas · WattBridge Texas Holding, LLC
600 MWIn study Angelina, TXERCOT Oct 2023target 2028
Capoterra BESS
Battery storage
600 MWPaused / redesign Milam, TXERCOT Jun 2022
Tehuacana Wind
Onshore wind
600 MWPaused / redesign Limestone, TXERCOT Jun 2017
Sitges Wind
Onshore wind · NextEra Energy Interconnection Holdings, LLC
600 MWIn study Motley, TXERCOT Mar 2024target 2029
Proteus London-Leigh Solar SLF
Solar + storage · London Leigh Solar, LLC
600 MWIn study Glasscock, TXERCOT Mar 2024target 2028
Capoterra
Solar
598 MWPaused / redesign Milam, TXERCOT Jun 2022
Brittlebush BESS
Battery storage
597 MWPaused / redesign Henderson, TXERCOT Jun 2022
Brittlebush Solar
Solar
594 MWPaused / redesign Henderson, TXERCOT Jun 2022
Jenna Eco-Electric Solar
Solar · Clean Energy Holdings, LLC
576 MWIn study Fisher, TXERCOT May 2024target 2028
RAYBURN ENERGY STATION II Gas (TEF-Due Diligence)
Gas · Rayburn Energy Station LLC
570 MWIn study Grayson, TXERCOT Jan 2025target 2028
Rio Vista Solar
Solar + storage · Rio Vista Solar, LLC
554 MWIn study Pecos, TXERCOT Jun 2025target 2028
Miller Bend Energy BESS
Solar + storage · Miller Bend Energy
548 MWIn study Young, TXERCOT Dec 2025target 2029
Miller Bend Energy Solar
Solar + storage · Miller Bend Energy
532 MWIn study Young, TXERCOT Dec 2025target 2029
Mojo Solar
Solar + storage · Power Synergy
528 MWIn study Wilson, TXERCOT Mar 2025target 2028
Toce TX BESS 2
Battery storage · TOCE TX BESS 2, LLC
523 MWIn study Wharton, TXERCOT Feb 2024target 2027
Tall Saddle Wind
Onshore wind · Tall Saddle Wind, LLC
523 MWIn study Kenedy, TXERCOT Jul 2024target 2029
Knight Airport BESS I
Battery storage · Airport Storage I LLC
523 MWIn study Harris, TXERCOT Aug 2024target 2027
Falcon BESS
Battery storage · Falcon Energy Project, LLC
517 MWIn study Zapata, TXERCOT Sep 2025target 2028
Ochoa Energy Storage II
Battery storage · Ochoa Energy Storage II LLC
517 MWIn study Waller, TXERCOT Apr 2024target 2029
Catamount Storage
Battery storage · TOCE TX BESS 3, LLC
515 MWIn study Harris, TXERCOT Sep 2024target 2028
Seven Angels Energy Storage II
Battery storage · Seven Angels Infrastructure LLC
514 MWIn study Hill, TXERCOT Nov 2025target 2028
Seven Angels Energy Storage I
Battery storage · Seven Angels Infrastructure LLC
514 MWIn study Hill, TXERCOT Nov 2025target 2028
Point Mountain Solar
Solar
514 MWPaused / redesign Upton, TXERCOT Jul 2022target 2026
Page 2 of 30

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)