Requests shown10024.5 GW
Active in queue24.5 GW100 requests
Agreement signed4,628 MW30 requests
Withdrawn18438.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

100 requests Β· page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project CSU-2020-3, El Paso County
Solar + storage
200 MWIn study El Paso, COWest Jun 2020target 2025
Solar project G0645, Klickitat County
Solar
200 MWIn study Klickitat, WAWest Mar 2020target 2026
Solar + storage project Q333, Navajo County
Solar + storage
200 MWIn study Navajo, AZWest Mar 2020target 2024
Solar project GI-2020-01, Pueblo County
Solar
199 MWPaused / redesign Pueblo, COWest Mar 2020target 2023
Solar project GI-2020-03, Pueblo County
Solar
199 MWPaused / redesign Pueblo, COWest Mar 2020target 2023
Battery storage project G0637, Klickitat County
Battery storage
190 MWIn study Klickitat, WAWest Jan 2020target 2022
Gas project 378, Yellowstone County
Gas
175 MWIn study Yellowstone, MTWest May 2020target 2023
Solar project G0654, Lake County
Solar
170 MWIn study Lake, ORWest Aug 2020target 2027
Battery storage project Q357, Maricopa County
Battery storage
150 MWUnder construction Maricopa, AZWest Sep 2020target 2023
Battery storage project IA-PNM-2020-17, Bernalillo County
Battery storage Β· AES Renewable Holdings
150 MWAgreement signed Bernalillo, NMWest Sep 2020target 2023
Onshore wind project IA-PNM-2020-01, Guadalupe County
Onshore wind
145 MWAgreement signed Guadalupe, NMWest Jan 2020target 2021
Solar + storage project 5, Grant County
Solar + storage
130 MWAgreement signed Grant, WAWest Jul 2020
Solar project 588, Ada County
Solar Β· PVS 2, LLC
125 MWAgreement signed Ada, IDWest Sep 2020target 2026
Onshore wind project 104, Spokane County
Onshore wind
120 MWIn study Spokane, WAWest Mar 2020target 2023
Onshore wind project G0635, Benton County
Onshore wind
100 MWIn study Benton, WAWest Jan 2020target 2021
Battery storage project 86, Whatcom County
Battery storage
100 MWAgreement signed Whatcom, WAWest Jul 2020target 2030
Solar project 20-02261, Larimer County
Solar
100 MWIn study Larimer, COWest Feb 2020target 2023
Battery storage project Q358, Maricopa County
Battery storage
100 MWAgreement signed Maricopa, AZWest Sep 2020target 2024
Zinnia Storage
Battery storage
100 MWAgreement signed Bernalillo, NMWest Oct 2020target 2023
Solar + storage project IA-PNM-2020-07, San Juan County
Solar + storage
100 MWIn study San Juan, NMWest May 2020target 2023
Battery storage project 81, Pierce County
Battery storage
100 MWPaused / redesign Pierce, WAWest Apr 2020target 2028
Battery storage project Q363, Maricopa County
Battery storage
100 MWIn study Maricopa, AZWest Sep 2020target 2023
Solar + storage project IA-PNM-2020-21, Valencia County
Solar + storage
100 MWAgreement signed Valencia, NMWest Oct 2020target 2023
Solar + storage project IA-PNM-2020-06, Mckinley County
Solar + storage
90.0 MWIn study Mckinley, NMWest May 2020target 2023
Ambrosia Solar
Solar + storage Β· Ambrosia Solar
90.0 MWPaused / redesign Mckinley, NMWest Oct 2020target 2023
Wildcat Solar Power Plant
Solar + storage
90.0 MWPaused / redesign Mckinley, NMWest Oct 2020target 2023
Gas project IA-PNM-2020-05, San Juan County
Gas Β· PNM β€šΓ„Γ¬ Generation
80.0 MWAgreement signed San Juan, NMWest Jan 2020target 2022
Other project GI-2020-139, Riverside County
Other
80.0 MWIn study Riverside, CAWest Nov 2020target 2027
Other project 72, Pima County
Other
80.0 MWIn study Pima, AZWest Jan 2020target 2022
Iris Del Sol
Solar + storage
76.0 MWAgreement signed Otero, NMWest Oct 2020target 2023
Battery storage project 1RSC-2020-02, Pueblo County
Battery storage
75.0 MWAgreement signed Pueblo, COWest Jan 2020target 2022
Solar project BHCT G28, Pueblo County
Solar
75.0 MWIn study Pueblo, COWest Feb 2020target 2023
Battery storage project 376, Yellowstone County
Battery storage
58.8 MWPaused / redesign Yellowstone, MTWest May 2020target 2023
Solar + storage project Q339, Yavapai County
Solar + storage
53.0 MWPaused / redesign Yavapai, AZWest Mar 2020target 2022
Geothermal project GI-2020-130, Imperial County
Geothermal
50.0 MWIn study Imperial, CAWest Jan 2020target 2028
Solar project Q346, Maricopa County
Solar
45.0 MWPaused / redesign Maricopa, AZWest Apr 2020target 2021
Solar + storage project TCS-54, Crook County
Solar + storage Β· SSEV C LLC
40.0 MWAgreement signed Crook, ORWest Apr 2020target 2026
Geothermal project Company KJ, Washoe County
Geothermal
38.5 MWAgreement signed Washoe, NVWest Feb 2020target 2023
Geothermal project Company KI, Washoe County
Geothermal
38.5 MWAgreement signed Washoe, NVWest Feb 2020target 2025
Geothermal project Company KH, Esmeralda County
Geothermal
38.5 MWAgreement signed Esmeralda, NVWest Feb 2020target 2022
Geothermal project Company KG, Eureka County
Geothermal
38.5 MWAgreement signed Eureka, NVWest Feb 2020target 2027
Gas project 377, Silver Bow County
Gas
36.0 MWPaused / redesign Silver Bow, MTWest May 2020target 2022
Gas project Q66, Maricopa County
Gas
30.0 MWIn study Maricopa, AZWest Nov 2020target 2022
Gas project Q65, Maricopa County
Gas
30.0 MWIn study Maricopa, AZWest Nov 2020target 2022
Gas project GI-2020-05, Weld County
Gas
24.0 MWAgreement signed Weld, COWest Mar 2020target 2020
Solar project TCS-52, Crook County
Solar Β· Get Along Solar II LLC
20.0 MWAgreement signed Crook, ORWest Apr 2020target 2026
Solar project TCS-53, Crook County
Solar Β· Get Along Solar XI LLC
20.0 MWAgreement signed Crook, ORWest Apr 2020target 2026
Gas project Q64, Pinal County
Gas
17.0 MWIn study Pinal, AZWest Jun 2020target 2020
Geothermal project Company KO, Lyon County
Geothermal
4.8 MWAgreement signed Lyon, NVWest Sep 2020target 2027
Hydro project GI-2020-18, Mesa County
Hydro
4.5 MWAgreement signed Mesa, COWest Dec 2020target 2022
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)