United States › Grid › Interconnection queues › Indiana
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in Indiana, PJM — page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project AI1-080, Laporte County Solar + storage |
125 MW | In study |
| Riverstart Solar Park II Solar |
125 MW | Agreement signed |
| Bluestem Solar Solar · RWE Solar Development, LLC |
125 MW | In study |
| Bluestem Solar Solar |
125 MW | Agreement signed |
| Rainbow Trout Solar + storage |
120 MW | Agreement signed |
| Solar project AG2-491, White County Solar · Black Prairie Solar Park II LLC |
100 MW | In study |
| Elkhart County Solar Project Solar |
100 MW | Agreement signed |
| Battery storage project AG2-332, Elkhart County Battery storage · Amberjack Solar LLC |
100 MW | In study |
| Flatrock Creek Solar II Solar |
100 MW | Agreement signed |
| Headwaters Wind Farm III Onshore wind |
100 MW | Paused / redesign |
| Madison County Solar Solar |
100 MW | Paused / redesign |
| Battery storage project AG2-343, Fountain County Battery storage · Dolphin Solar LLC |
100 MW | In study |
| Prairie Creek Wind Phase 2 Onshore wind · Prairie Creek Wind Farm II, LLC |
100 MW | Agreement signed |
| Flatrock Creek Solar I Solar |
100 MW | Agreement signed |
| Solar project AG2-550, Randolph County Solar · Riverstart Solar Park VI LLC |
100 MW | In study |
| Headwaters Wind Farm III Onshore wind |
100 MW | Paused / redesign |
| Solar + storage project AI1-081, Jay County Solar + storage |
100 MW | In study |
| Tillman Solar Park Solar |
100 MW | Agreement signed |
| Battery storage project AH2-233, Pulaski County Battery storage |
100 MW | In study |
| Riverstart Solar Park V Solar |
100 MW | Paused / redesign |
| Battery storage project AG2-248, Elkhart County Battery storage · Amberjack Solar LLC |
100 MW | In study |
| Solar + storage project AI1-009, Rush County Solar + storage |
100 MW | In study |
| Sun Chief Solar Farm Solar |
100 MW | Agreement signed |
| Solar project AH1-392, St. Joseph County Solar · ibV Energy Partners LLC |
90.0 MW | In study |
| Solar project AI2-115, Delaware County Solar |
84.0 MW | In study |
| Hawthorn Solar Solar |
83.0 MW | Agreement signed |
| Fall Creek Energy Storage Battery storage |
80.0 MW | Agreement signed |
| Battery storage project AH1-482, Pulaski County Battery storage · Lightsource Renewable Energy Development, LLC |
78.0 MW | In study |
| Battery storage project AH2-227, Jay County Battery storage |
75.0 MW | In study |
| Battery storage project AH1-302, Pulaski County Battery storage · Bottlebrush Solar Energy LLC |
75.0 MW | In study |
| BR Solar Sheriff 1 Solar |
75.0 MW | Agreement signed |
| Solar + storage project AG2-519, Delaware County Solar + storage · Muncie Solar 1, LLC |
66.5 MW | In study |
| Dover Solar Facility Solar |
55.0 MW | Paused / redesign |
| Bluestem Solar Battery storage · RWE Solar Development, LLC |
55.0 MW | In study |
| Gas project AG2-562, St. Joseph County Gas · St. Joseph Energy Center, LLC |
52.0 MW | In study |
| Battery storage project AG2-370, Allen County Battery storage · Tillman Storage LLC |
50.0 MW | In study |
| Flatrock Creek Storage I Battery storage |
50.0 MW | Agreement signed |
| Battery storage project AG2-551, Randolph County Battery storage · Riverstart Solar Park VI LLC |
50.0 MW | In study |
| Solar project AH2-223, Jay County Solar |
50.0 MW | In study |
| Trade Post Energy Storage Battery storage |
50.0 MW | Agreement signed |
| Solar project AH1-153, St. Joseph County Solar · Dumont Solar, LLC |
50.0 MW | In study |
| Battery storage project AG2-345, Fountain County Battery storage · Dolphin Solar LLC |
50.0 MW | In study |
| Battery storage project AG2-014, White County Battery storage · Black Prairie Storage LLC |
50.0 MW | In study |
| Battery storage project AG2-492, White County Battery storage · Black Prairie Storage II LLC |
50.0 MW | In study |
| Battery storage project AH2-371, Jay County Battery storage |
50.0 MW | In study |
| Solar project AI2-161, Vermillion County Solar |
48.0 MW | In study |
| Solar project AI2-162, Whitley County Solar |
48.0 MW | In study |
| Lake Trout Solar Solar |
45.0 MW | Agreement signed |
| Solar project AI2-150, Huntington County Solar |
44.4 MW | In study |
| Solar project AI2-421, Dekalb County Solar |
43.2 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)182 · 41.7 GW
- PJM (Mid-Atlantic, Midwest)117 · 17.4 GW
- Southeast (non-ISO utilities)1 · 500 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)