Solar project J1306, Perry County Solar |
200 MW | Agreement signed |
Perry, IL | MISO |
Apr 2019 | target 2024 |
Solar project J1381, Howard County Solar |
200 MW | Agreement signed |
Howard, IN | MISO |
Apr 2019 | target 2026 |
Solar project J1348, Vermillion County Solar |
200 MW | Agreement signed |
Vermillion, IN | MISO |
Apr 2019 | target 2025 |
Solar + storage project J1340, Jasper County Solar + storage |
200 MW | Agreement signed |
Jasper, IN | MISO |
Apr 2019 | target 2025 |
Solar + storage project J1336, Jasper County Solar + storage |
200 MW | Agreement signed |
Jasper, IN | MISO |
Apr 2019 | target 2025 |
Solar + storage project J1339, Jasper County Solar + storage |
200 MW | Agreement signed |
Jasper, IN | MISO |
Apr 2019 | target 2025 |
Onshore wind project J1292, Ionia County Onshore wind |
198 MW | Agreement signed |
Ionia, MI | MISO |
Apr 2019 | target 2024 |
Solar project J1658, Hillsdale County Solar |
180 MW | Agreement signed |
Hillsdale, MI | MISO |
May 2025 | target 2025 |
Solar project J643, Jasper County Solar |
175 MW | Agreement signed |
Jasper, IN | MISO |
May 2016 | 2023 |
Solar project J1583, Iberville Parish County Solar |
175 MW | Agreement signed |
Iberville Parish, LA | MISO |
Jun 2020 | target 2025 |
Solar project J586, Mississippi County Solar |
175 MW | Agreement signed |
Mississippi, AR | MISO |
May 2016 | 2024 |
Solar project MPC03600, Richland County Solar |
170 MW | Agreement signed |
Richland, ND | MISO |
May 2018 | target 2027 |
Onshore wind project J1175, Worth County Onshore wind |
165 MW | Agreement signed |
Worth, IA | MISO |
Mar 2018 | target 2024 |
Battery storage project J1355, Laporte County Battery storage |
160 MW | Agreement signed |
Laporte, IN | MISO |
Apr 2019 | target 2026 |
Onshore wind project MPC03900, Eddy County Onshore wind |
151 MW | Agreement signed |
Eddy, ND | MISO |
Apr 2019 | target 2027 |
Solar project J1751, Wood County Solar |
151 MW | Agreement signed |
Wood, WI | MISO |
Apr 2022 | target 2026 |
Solar project J1027, Pike County Solar |
150 MW | Agreement signed |
Pike, IN | MISO |
Mar 2018 | target 2022 |
Solar project J1553, Clinton County Solar |
150 MW | Agreement signed |
Clinton, MI | MISO |
Dec 2021 | target 2025 |
Solar project J1482, White County Solar |
150 MW | Agreement signed |
White, IN | MISO |
Apr 2019 | 2024 |
Solar project J1383, Fulton County Solar |
150 MW | Agreement signed |
Fulton, IL | MISO |
Apr 2019 | target 2025 |
Solar project J1465, Pointe Coupee Parish County Solar |
150 MW | Agreement signed |
Pointe Coupee Parish, LA | MISO |
Apr 2019 | target 2024 |
Solar project J1615, Oconto County Solar |
150 MW | Agreement signed |
Oconto, WI | MISO |
Jun 2020 | target 2026 |
Solar project J1302, Saline County Solar |
150 MW | Agreement signed |
Saline, IL | MISO |
Apr 2019 | target 2025 |
Solar project J1028, Pike County Solar |
150 MW | Agreement signed |
Pike, IN | MISO |
Mar 2018 | target 2022 |
Solar project J1672, Hinds County Solar |
150 MW | Agreement signed |
Hinds, MS | MISO |
Jun 2020 | target 2025 |
Solar project J1746, Columbia County Solar |
150 MW | Agreement signed |
Columbia, WI | MISO |
Jun 2020 | target 2028 |
Solar project J1794, Acadia Parish County Solar |
150 MW | Agreement signed |
Acadia Parish, LA | MISO |
Jun 2020 | target 2025 |
Solar project J1382, Clark County Solar |
150 MW | Agreement signed |
Clark, IL | MISO |
Apr 2019 | target 2025 |
Solar project J1303, Jackson County Solar |
150 MW | Agreement signed |
Jackson, IL | MISO |
Apr 2019 | target 2026 |
Solar project J1268, Lincoln County Solar |
150 MW | Agreement signed |
Lincoln, MO | MISO |
Apr 2019 | target 2023 |
Solar + storage project J1422, Edwards County Solar + storage |
150 MW | Agreement signed |
Edwards, IL | MISO |
Apr 2019 | target 2024 |
Solar project J1311, St. Clair County Solar |
150 MW | Agreement signed |
St. Clair, IL | MISO |
Apr 2019 | target 2025 |
Solar project J1139, Champaign County Solar |
150 MW | Agreement signed |
Champaign, IL | MISO |
Mar 2018 | target 2023 |
Solar project J1450, Webster County Solar |
150 MW | Agreement signed |
Webster, KY | MISO |
Apr 2019 | target 2025 |
Battery storage project J1357, Madison County Battery storage |
150 MW | Agreement signed |
Madison, IN | MISO |
Apr 2019 | target 2025 |
Solar project J1320, Branch County Solar |
150 MW | Agreement signed |
Branch, MI | MISO |
Apr 2019 | target 2025 |
Solar project J1388, Gibson County Solar |
150 MW | Agreement signed |
Gibson, IN | MISO |
Apr 2019 | target 2024 |
Solar project J986, Wood County Solar |
150 MW | Agreement signed |
Wood, WI | MISO |
Mar 2018 | 2023 |
Battery storage project J1354, Decatur County Battery storage |
146 MW | Agreement signed |
Decatur, IN | MISO |
Apr 2019 | target 2025 |
Solar project J641, Morgan County Solar |
140 MW | Agreement signed |
Morgan, IL | MISO |
May 2016 | 2024 |
Solar project J1542, St. James Parish County Solar |
135 MW | Agreement signed |
St. James Parish, LA | MISO |
Jun 2020 | target 2026 |
Gas project H037, Lucas County Gas |
135 MW | Agreement signed |
Lucas, OH | MISO |
May 2008 | target 2010 |
Solar project MPC03700, Richland County Solar |
130 MW | Agreement signed |
Richland, ND | MISO |
May 2018 | target 2027 |
Solar project J1393, Pike County Solar |
130 MW | Agreement signed |
Pike, IN | MISO |
Apr 2019 | target 2026 |
Battery storage project J1358, Laporte County Battery storage |
125 MW | Agreement signed |
Laporte, IN | MISO |
Apr 2019 | target 2026 |
Solar project J1389, Saginaw County Solar |
120 MW | Agreement signed |
Saginaw, MI | MISO |
Apr 2019 | target 2025 |
Gas project J1833, Lafourche Parish County Gas |
115 MW | Agreement signed |
Lafourche Parish, LA | MISO |
Oct 2021 | target 2025 |
Solar project J644, Greene County Solar |
110 MW | Agreement signed |
Greene, IL | MISO |
May 2016 | 2024 |
Solar project J1234, Knox County Solar |
100 MW | Agreement signed |
Knox, IN | MISO |
Apr 2019 | target 2023 |
Solar project J603, Ashley County Solar |
100 MW | Agreement signed |
Ashley, AR | MISO |
May 2016 | 2024 |