OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2022 requests) โ€” page 19

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,886378.9 GW
Active in queue299.4 GW1,514 requests
Agreement signed43.0 GW228 requests
Withdrawn1,886378.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,886 requests ยท page 19 of 38
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 505, Franklin County
Solar + storage
146 MWWithdrawn / abandoned Franklin, TNSoutheast Jun 2022
Trigo Solar Project
Solar ยท Ignis TX Solar Two LLC
146 MWWithdrawn / abandoned ERCOT Jan 2022target 2025
Solar project J3103, Fountain County
Solar
145 MWWithdrawn / abandoned Fountain, INMISO Jun 2022target 2026
Onshore wind project J2323, Webster County
Onshore wind
145 MWWithdrawn / abandoned Webster, IAMISO Sep 2022target 2027
Solar project 684, Minidoka County
Solar
145 MWWithdrawn / abandoned Minidoka, IDWest Nov 2022target 2026
Onshore wind project J3091, Logan County
Onshore wind
145 MWWithdrawn / abandoned Logan, NDMISO Sep 2022target 2026
Solar + storage project J2615, Warren County
Solar + storage
145 MWWithdrawn / abandoned Warren, INMISO Sep 2022target 2026
Battery storage project 513, Maury County
Battery storage
145 MWWithdrawn / abandoned Maury, TNSoutheast Aug 2022target 2027
Onshore wind project J2919, Montgomery County
Onshore wind
143 MWWithdrawn / abandoned Montgomery, INMISO Sep 2022target 2027
Battery storage project J2531, Union Parish County
Battery storage
140 MWWithdrawn / abandoned Union Parish, LAMISO Sep 2022target 2026
Solar project 686, Blaine County
Solar
140 MWWithdrawn / abandoned Blaine, IDWest Nov 2022
Onshore wind project 130, Garfield County
Onshore wind
140 MWWithdrawn / abandoned Garfield, WAWest Feb 2022target 2025
Battery storage project J2527, Allen Parish County
Battery storage
140 MWWithdrawn / abandoned Allen Parish, LAMISO Sep 2022target 2025
Battery storage project Q97, Maricopa County
Battery storage
140 MWWithdrawn / abandoned Maricopa, AZWest Sep 2022target 2025
Solar project 680, Twin Falls County
Solar
140 MWWithdrawn / abandoned Twin Falls, IDWest Oct 2022
Solar + storage project J3071, St. Francis County
Solar + storage
140 MWWithdrawn / abandoned St. Francis, ARMISO Sep 2022target 2024
Battery storage project J2943, Webster Parish County
Battery storage
140 MWWithdrawn / abandoned Webster Parish, LAMISO Sep 2022target 2026
Solar project AH2-213, Randolph County
Solar
140 MWWithdrawn / abandoned Randolph, INPJM Mar 2022target 2026
Solar + storage project 678, Power County
Solar + storage
140 MWWithdrawn / abandoned Power, IDWest Oct 2022
Battery storage project J2479, Concordia Parish County
Battery storage
140 MWWithdrawn / abandoned Concordia Parish, LAMISO Sep 2022target 2025
Battery storage project J2489, Red River Parish County
Battery storage
140 MWWithdrawn / abandoned Red River Parish, LAMISO Sep 2022target 2026
Solar project J1876, Decatur County
Solar
140 MWWithdrawn / abandoned Decatur, INMISO Mar 2022target 2024
Battery storage project J3046, Concordia Parish County
Battery storage
140 MWWithdrawn / abandoned Concordia Parish, LAMISO Sep 2022target 2025
Solar project AH2-170, Will County
Solar
140 MWWithdrawn / abandoned Will, ILPJM Mar 2022target 2026
Battery storage project J2418, Marshall County
Battery storage
140 MWWithdrawn / abandoned Marshall, INMISO Sep 2022target 2025
Solar + storage project J2727, Holmes County
Solar + storage
140 MWWithdrawn / abandoned Holmes, MSMISO Sep 2022target 2025
Battery storage project 565492, Nash County
Battery storage ยท Duke Energy Progress, LLC
138 MWWithdrawn / abandoned Nash, NCSoutheast Jun 2022
Solar project GEN-2022-053, Barton County
Solar
138 MWWithdrawn / abandoned Barton, MOSPP Jun 20222025
Solar project AI1-104, Paulding County
Solar
135 MWWithdrawn / abandoned Paulding, OHPJM Aug 2022target 2029
Solar project GEN-2022-002, Finney County
Solar
135 MWWithdrawn / abandoned Finney, KSSPP May 2022target 2026
Solar project J3148, Greene County
Solar
131 MWWithdrawn / abandoned Greene, IAMISO Sep 2022target 2027
Sunshine Solar
Solar ยท Sunshine Energy LLC
131 MWWithdrawn / abandoned ERCOT Sep 2022target 2026
Solar project J2560, Sunflower County
Solar
130 MWWithdrawn / abandoned Sunflower, MSMISO Sep 2022target 2027
Mulberry Energy Storage
Battery storage ยท Mulberry Energy Storage 1, LLC
130 MWWithdrawn / abandoned Saratoga, NYNYISO Sep 2022
Solar + storage project J2688, Newton County
Solar + storage
130 MWWithdrawn / abandoned Newton, TXMISO Sep 2022target 2026
West Babylon
Battery storage ยท 174 Power Global Properties
130 MWWithdrawn / abandoned Nassau, NYNYISO Mar 2022
Solar + storage project J3226, Marshall County
Solar + storage
130 MWWithdrawn / abandoned Marshall, INMISO Sep 2022target 2026
Onshore wind project J2466, Howard County
Onshore wind
130 MWWithdrawn / abandoned Howard, IAMISO Sep 2022target 2027
Battery storage project J2646, Lincoln Parish County
Battery storage
130 MWWithdrawn / abandoned Lincoln Parish, LAMISO Sep 2022target 2026
Battery Storage
Battery storage
130 MWWithdrawn / abandoned Worcester, MAISO-NE Nov 2022target 2026
Battery storage project J2468, Union County
Battery storage
130 MWWithdrawn / abandoned Union, ARMISO Sep 2022target 2026
Solar + storage project J2290, Avoyelles Parish County
Solar + storage
130 MWWithdrawn / abandoned Avoyelles Parish, LAMISO Feb 2022target 2025
Solar + storage project J2903, Lincoln County
Solar + storage
130 MWWithdrawn / abandoned Lincoln, MSMISO Sep 2022target 2025
Battery Storage
Battery storage
130 MWWithdrawn / abandoned Berkshire, MAISO-NE Nov 2022target 2026
Solar plus Battery
Solar + storage
129 MWWithdrawn / abandoned Oxford, MEISO-NE Mar 2022target 2029
Gas project Company NM, Storey County
Gas
128 MWWithdrawn / abandoned Storey, NVWest Mar 2022target 2027
NY Wind - Mott Haven Uprate
Onshore wind ยท Bay State Wind
128 MWWithdrawn / abandoned Bronx, NYNYISO Nov 2022
Solar project J2331, Franklin County
Solar
127 MWWithdrawn / abandoned Franklin, ILMISO Sep 2022target 2026
Battery storage project 132, Thurston County
Battery storage
127 MWWithdrawn / abandoned Thurston, WAWest May 2022target 2033
Solar project AH2-237, Wells County
Solar
125 MWWithdrawn / abandoned Wells, INPJM Mar 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)