🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Massachusetts

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 130 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Berkshire County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2022 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1337
Grid region
ISO-NE (New England)
Connection point (POI)
7,500' to Adams - NG Q117 VEL - 65,000' Bennington 115 kV line (42.72482385, -73.09931100). (The project site is on the western side of the transmission line off a gravel bank road and on the opposi
Location
Berkshire County, Massachusetts
Technology
Battery: 130 MW
Total requested
130 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
22 November 2022
Proposed online date
December 2026
Withdrawn
November 2023

Location

Marker shows the centre of Berkshire County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Berkshire County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem