๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in the USA (2025 requests) โ€” page 13

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,836452.0 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,836 requests ยท page 13 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J3954, Christian County
Solar
250 MWIn study Christian, ILMISO Apr 2025target 2030
Battery storage project 25-IC-1334, Effingham County
Battery storage
250 MWIn study Effingham, GASoutheast Apr 2025target 2029
Onshore wind project J3929, Audrain County
Onshore wind
250 MWIn study Audrain, MOMISO Jan 2025target 2030
Battery storage project J4081, Grant County
Battery storage
250 MWIn study Grant, SDMISO Oct 2025target 2030
Solar + storage project GEN-2024-271, Chaves County
Solar + storage
250 MWIn study Chaves, NMSPP Mar 2025target 2029
Onshore wind project J4018, Ford County
Onshore wind
250 MWIn study Ford, ILMISO May 2025target 2029
Solar + storage project 793, Ada County
Solar + storage
250 MWIn study Ada, IDWest Apr 2025target 2029
Battery storage project GEN-2024-217, Jackson County
Battery storage
250 MWIn study Jackson, MOSPP Mar 2025target 2029
Solar project GEN-2024-139, Coffey County
Solar
250 MWIn study Coffey, KSSPP Mar 2025target 2033
Solar + storage project J4201, Beauregard Parish County
Solar + storage
250 MWIn study Beauregard Parish, LAMISO Sep 2025target 2029
Solar + storage project GEN-2024-281, Lea County
Solar + storage
250 MWIn study Lea, NMSPP Mar 2025target 2029
Onshore wind project GEN-2024-235, Payne County
Onshore wind
250 MWIn study Payne, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-371, Lea County
Battery storage
250 MWIn study Lea, NMSPP Mar 2025target 2028
Battery storage project GEN-2024-328, Slope County
Battery storage
250 MWIn study Slope, NDSPP Mar 2025target 2028
Battery storage project J3894, Lyon County
Battery storage
250 MWIn study Lyon, MNMISO Feb 2025target 2030
Battery storage project J4118, Mclean County
Battery storage
250 MWIn study Mclean, ILMISO Sep 2025target 2030
Battery storage project GEN-2024-372, Douglas County
Battery storage
250 MWIn study Douglas, NESPP Mar 2025target 2028
Battery storage project GEN-2024-370, Clay County
Battery storage
250 MWIn study Clay, MOSPP Mar 2025target 2028
Solar + storage project IA-PNM-2025-06, Bernalillo County
Solar + storage
250 MWIn study Bernalillo, NMWest Mar 2025target 2031
Solar + storage project 25RSC-009, Hardeman County
Solar + storage
250 MWIn study Hardeman, TNSoutheast Aug 2025target 2031
Solar project J4080, Jefferson County
Solar
250 MWIn study Jefferson, ARMISO Oct 2025target 2030
Battery storage project GEN-2024-176, Reno County
Battery storage
250 MWIn study Reno, KSSPP Mar 2025target 2028
Solar project AG2-029, Noble County
Solar ยท Southern Pike Solar LLC
250 MWIn study Noble, INPJM Feb 2025target 2024
Solar project AG2-163, Fountain County
Solar ยท Dolphin Solar LLC
250 MWIn study Fountain, INPJM Feb 2025target 2024
Solar project J3882, Crawford County
Solar
250 MWIn study Crawford, ILMISO Feb 2025target 2030
Solar project J3911, Louisa County
Solar
250 MWIn study Louisa, IAMISO Feb 2025target 2030
Onshore wind project GEN-2024-193, Ford County
Onshore wind
250 MWIn study Ford, KSSPP Mar 2025target 2028
Onshore wind project GEN-2024-194, Ford County
Onshore wind
250 MWIn study Ford, KSSPP Mar 2025target 2028
Solar + storage project T2-053, Iron County
Solar + storage
248 MWIn study Iron, UTWest Sep 2025target 2029
FERMI Storage Project
Battery storage ยท DTE Electric
248 MWIn study Monroe, MIMISO Aug 2025target 2028
Gas project GEN-2024-293, Oklahoma County
Gas
248 MWIn study Oklahoma, OKSPP Mar 2025target 2033
Bluewind BESS
Battery storage ยท Bluewind Energy Center, LLC
247 MWIn study Atascosa, TXERCOT Apr 2025target 2029
Mojo BESS
Solar + storage ยท Power Synergy
246 MWIn study Wilson, TXERCOT Apr 2025target 2028
Apricot Sun Solar
Solar + storage ยท Apricot Sun Energy Center, LLC
246 MWIn study Duval, TXERCOT Apr 2025target 2029
Dempsey Solar SLF
Solar + storage ยท Dempsey Solar LLC
245 MWIn study Leon, TXERCOT Feb 2025target 2028
Solar project J4031, Scott County
Solar
245 MWIn study Scott, ILMISO May 2025target 2030
Solar project J3945, Washtenaw County
Solar
245 MWIn study Washtenaw, MIMISO Apr 2025target 2030
Solar project J4147, Clay County
Solar
245 MWIn study Clay, MNMISO Oct 2025target 2030
Solar project J4001, Marion County
Solar
245 MWIn study Marion, MOMISO Apr 2025target 2030
Solar project J3949, Scott County
Solar
245 MWIn study Scott, ILMISO Apr 2025target 2030
Solar project J4148, Clay County
Solar
245 MWIn study Clay, MNMISO Oct 2025target 2030
Solar project J3961, Lincoln County
Solar
245 MWIn study Lincoln, MNMISO Apr 2025target 2030
Brazos Bend Solar SLF
Solar + storage ยท Grenergy USA
243 MWIn study Milam, TXERCOT Sep 2025target 2029
Brazos Bend Storage SLF
Solar + storage ยท Grenergy USA
243 MWIn study Milam, TXERCOT Sep 2025target 2029
Onshore wind project GEN-2024-236, Okfuskee County
Onshore wind
241 MWIn study Okfuskee, OKSPP Mar 2025target 2029
Battery storage project J4117, Goodhue County
Battery storage
240 MWIn study Goodhue, MNMISO Sep 2025target 2030
Gas project 25-IC-1320A, Lee County
Gas
240 MWIn study Lee, ALSoutheast Apr 2025target 2029
Other project GEN-2025-SR10, Seminole County
Other
238 MWIn study Seminole, OKSPP May 2025target 2030
Kuy Creek Solar 1 SLF
Solar + storage ยท Kuy Creek Solar 1 LLC
235 MWIn study Goliad, TXERCOT Apr 2025target 2029
Gas project ERAS-2025-016, Lamb County
Gas
233 MWIn study Lamb, TXSPP Oct 2025target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)