United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2017 requests) โ€” page 12

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,258161.7 GW
Active in queue51.0 GW292 requests
Agreement signed32.8 GW182 requests
Withdrawn1,258161.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,258 requests ยท page 12 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 327, Stillwater County
Onshore wind
80.0 MWWithdrawn / abandoned Stillwater, MTWest Jul 2017target 2021
Onshore wind project 868, Rich County
Onshore wind
80.0 MWWithdrawn / abandoned Rich, UTWest Apr 2017target 2019
Solar project 924, Klamath County
Solar
80.0 MWWithdrawn / abandoned Klamath, ORWest Aug 2017target 2019
Onshore wind project 867, Carbon County
Onshore wind
80.0 MWWithdrawn / abandoned Carbon, UTWest Apr 2017target 2019
Solar + storage project 915, Klamath County
Solar + storage
80.0 MWWithdrawn / abandoned Klamath, ORWest Jul 2017target 2019
Solar project 18052, Sampson County
Solar ยท Masked
80.0 MWWithdrawn / abandoned Sampson, NCSoutheast Oct 2017
Onshore wind project 855, Converse County
Onshore wind
80.0 MWWithdrawn / abandoned Converse, WYWest Mar 2017target 2019
Hill Solar
Solar ยท Sunchase Power
80.0 MWWithdrawn / abandoned Hill, TXERCOT Sep 2017target 2022
Solar project AD1-126, Dekalb County
Solar
80.0 MWWithdrawn / abandoned Dekalb, ILPJM Sep 2017target 2020
Solar project J856, Vanderburgh County
Solar
80.0 MWWithdrawn / abandoned Vanderburgh, INMISO Jun 2017target 2021
Solar project IC-576, Clarke County
Solar
80.0 MWWithdrawn / abandoned Clarke, MSSoutheast Jan 2017
Onshore wind project J883, Pulaski County
Onshore wind
80.0 MWWithdrawn / abandoned Pulaski, INMISO Jun 2017target 2022
Onshore wind project AD1-069, Fayette County
Onshore wind
80.0 MWWithdrawn / abandoned Fayette, PAPJM Aug 2017target 2020
Solar project GI-2017-9, Pueblo County
Solar
80.0 MWWithdrawn / abandoned Pueblo, COWest Feb 2017target 2019
Solar project IC-633, Appling County
Solar
80.0 MWWithdrawn / abandoned Appling, GASoutheast Apr 2017
Solar project 18049, Sampson County
Solar ยท Masked
80.0 MWWithdrawn / abandoned Sampson, NCSoutheast Oct 2017
Onshore wind project 312, Wheatland County
Onshore wind
80.0 MWWithdrawn / abandoned Wheatland, MTWest Feb 2017target 2019
Solar project IC-650, Perry County
Solar
80.0 MWWithdrawn / abandoned Perry, ALSoutheast Aug 2017
Solar project AC2-159, Northampton County
Solar
80.0 MWWithdrawn / abandoned Northampton, NCPJM Mar 2017target 2019
Solar project IC-574, Tattnall County
Solar
80.0 MWWithdrawn / abandoned Tattnall, GASoutheast Jan 2017
Coldwater Solar
Solar ยท EDP Renewables North America LLC
80.0 MWWithdrawn / abandoned Chautauqua, NYNYISO Sep 2017
Solar project IC-617, Bryan County
Solar
80.0 MWWithdrawn / abandoned Bryan, GASoutheast Mar 2017
Solar project G0562, Yakima County
Solar
80.0 MWWithdrawn / abandoned Yakima, WAWest May 2017target 2019
Solar + storage project TCS-06, Fremont County
Solar + storage ยท Fresh Air Energy II, LLC
80.0 MWWithdrawn / abandoned Fremont, WYWest Sep 2017target 2027
Onshore wind project 333, Wheatland County
Onshore wind
80.0 MWWithdrawn / abandoned Wheatland, MTWest Aug 2017target 2021
Solar + storage project 917, Klamath County
Solar + storage
80.0 MWWithdrawn / abandoned Klamath, ORWest Jul 2017target 2019
Onshore wind project 328, Stillwater County
Onshore wind
80.0 MWWithdrawn / abandoned Stillwater, MTWest Jul 2017target 2021
Solar project 17658, Marion County
Solar
80.0 MWWithdrawn / abandoned Marion, SCSoutheast Oct 2017
Solar project J865, St. Clair County
Solar
80.0 MWWithdrawn / abandoned St. Clair, MIMISO Jun 2017target 2020
Onshore wind project 17-08072, Larimer County
Onshore wind
80.0 MWWithdrawn / abandoned Larimer, COWest Aug 2017target 2019
Solar project IC-607, Seminole County
Solar
80.0 MWWithdrawn / abandoned Seminole, GASoutheast Mar 2017
Solar project G0564, Franklin County
Solar
80.0 MWWithdrawn / abandoned Franklin, WAWest May 2017target 2019
Solar project IC-638, Elmore County
Solar
80.0 MWWithdrawn / abandoned Elmore, ALSoutheast May 2017
Solar + storage project 916, Klamath County
Solar + storage
80.0 MWWithdrawn / abandoned Klamath, ORWest Jul 2017target 2019
Solar project AC2-102, Culpeper County
Solar
80.0 MWWithdrawn / abandoned Culpeper, VAPJM Mar 2017target 2019
Solar project AC2-182, Franklin County
Solar
80.0 MWWithdrawn / abandoned Franklin, PAPJM Mar 2017target 2018
Solar project 996, Box Elder County
Solar
80.0 MWWithdrawn / abandoned Box Elder, UTWest Dec 2017target 2020
Onshore wind project AD1-068, Preston County
Onshore wind
80.0 MWWithdrawn / abandoned Preston, WVPJM Aug 2017target 2020
Battery storage project GEN-2017-197, Woodward County
Battery storage
80.0 MWWithdrawn / abandoned Woodward, OKSPP Nov 20172022
Solar project IC-610, Lowndes County
Solar
79.5 MWWithdrawn / abandoned Lowndes, ALSoutheast Mar 2017
Solar project IC-609, Barbour County
Solar
79.5 MWWithdrawn / abandoned Barbour, ALSoutheast Mar 2017
Solar project 336, Haywood County
Solar
79.0 MWWithdrawn / abandoned Haywood, TNSoutheast Dec 2017
Solar project IC-647, Macon County
Solar
78.6 MWWithdrawn / abandoned Macon, ALSoutheast Jul 2017
Solar project AD1-117, Ogle County
Solar
78.0 MWWithdrawn / abandoned Ogle, ILPJM Sep 2017target 2020
Solar project IC-596, Marengo County
Solar
78.0 MWWithdrawn / abandoned Marengo, ALSoutheast Feb 2017
Solar project IC-595, Marengo County
Solar
78.0 MWWithdrawn / abandoned Marengo, ALSoutheast Feb 2017
Solar project J917, Liberty County
Solar
78.0 MWWithdrawn / abandoned Liberty, TXMISO Jun 2017target 2019
Solar + storage project 865, Iron County
Solar + storage
77.5 MWWithdrawn / abandoned Iron, UTWest Apr 2017target 2020
Solar + storage project TCS-02, Iron County
Solar + storage
77.5 MWWithdrawn / abandoned Iron, UTWest Apr 2017target 2023
Solar + storage project 864, Iron County
Solar + storage
77.5 MWWithdrawn / abandoned Iron, UTWest Apr 2017target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)