United States βΊ Grid βΊ Interconnection queues βΊ Alabama
SOLAR Β· SOUTHEASTSolar project IC-609, Barbour County
Solar project IC-609, Barbour County is a 79.5 MW solar request withdrawn in the Southeast interconnection queue, in Barbour County, Alabama, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2017 (completed)
- Withdrawn / abandonedAug 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-609
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Eufaula - Fort Mitchell 115 kV Line
- Location
- Barbour County, Alabama
- Technology
- Solar: 79.5 MW
- Total requested
- 79.5 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 10 March 2017
- Withdrawn
- August 2018
Location
Marker shows the centre of Barbour County; the queue data does not give exact sites.