Solar project IC-650, Perry County

Solar project IC-650, Perry County is a 80.0 MW solar request withdrawn in the Southeast interconnection queue, in Perry County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2017 (completed)
  2. Withdrawn / abandonedMay 2021 (project stopped here)
  3. ConsentedApr 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-650
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Greene County - North Selma 230 kV Line
Location
Perry County, Alabama
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
16 August 2017
Agreement signed
30 April 2019
Withdrawn
May 2021

Location

Marker shows the centre of Perry County; the queue data does not give exact sites.

Power plants in Alabama Β· Transmission lines in Alabama

Other requests in Perry County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem