United States βΊ Grid βΊ Interconnection queues βΊ Michigan
SOLAR Β· MISOSolar project J865, St. Clair County
Solar project J865, St. Clair County is a 80.0 MW solar request withdrawn in the MISO interconnection queue, in St. Clair County, Michigan, connecting to ITC MIDWEST.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2017 (completed)
- Withdrawn / abandonedJan 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J865
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Lee - Menlo 120kV Line
- Location
- St. Clair County, Michigan
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 June 2017
- Proposed online date
- September 2020
- Withdrawn
- January 2019
Location
Marker shows the centre of St. Clair County; the queue data does not give exact sites.
Other requests in St. Clair County
- Solar project J1664, St. Clair CountySolar Β· 200 MW Β· agreement signed
- Solar project J1331, St. Clair CountySolar Β· 100 MW Β· agreement signed
- Battery storage project J3646, St. Clair CountyBattery storage Β· 220 MW Β· in study
- Battery storage project J2684, St. Clair CountyBattery storage Β· 200 MW Β· in study
- Solar project J2677, St. Clair CountySolar Β· 200 MW Β· in study
- Gas project J793, St. Clair CountyGas Β· 1,175 MW Β· built
- Gas project G042, St. Clair CountyGas Β· 332 MW Β· built
- Gas project G065, St. Clair CountyGas Β· 1,050 MW Β· withdrawn
- Other project G012, St. Clair CountyOther Β· 930 MW Β· withdrawn
- Gas project G137, St. Clair CountyGas Β· 560 MW Β· withdrawn
- Battery storage project J3460, St. Clair CountyBattery storage Β· 290 MW Β· withdrawn
- Solar project J1526, St. Clair CountySolar Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem