United States βΊ Grid βΊ Interconnection queues βΊ Alabama
SOLAR Β· SOUTHEASTSolar project IC-647, Macon County
Solar project IC-647, Macon County is a 78.6 MW solar request withdrawn in the Southeast interconnection queue, in Macon County, Alabama, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2017 (completed)
- Withdrawn / abandonedApr 2021 (project stopped here)
- ConsentedApr 2019 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-647
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Thurlow Dam - Union Springs 115 kV Line
- Location
- Macon County, Alabama
- Technology
- Solar: 78.6 MW
- Total requested
- 78.6 MW
- Service type
- Energy only (ERIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 24 July 2017
- Agreement signed
- 23 April 2019
- Withdrawn
- April 2021
Location
Marker shows the centre of Macon County; the queue data does not give exact sites.
Other requests in Macon County
- Solar project 25-IC-1367, Macon CountySolar Β· 195 MW Β· withdrawn
- Solar project IC-401, Macon CountySolar Β· 80.0 MW Β· withdrawn
- Solar + storage project IC-930, Macon CountySolar + storage Β· 79.0 MW Β· withdrawn
- Solar project IC-555, Macon CountySolar Β· 60.0 MW Β· withdrawn
- Solar project IC-556, Macon CountySolar Β· 25.0 MW Β· withdrawn
- Solar project IC-269, Macon CountySolar Β· 2.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem