Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,194150.9 GW
Active in queue25.8 GW162 requests
Agreement signed18.1 GW106 requests
Withdrawn1,194150.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,194 requests ยท page 12 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-509, Mitchell County
Solar
80.0 MWWithdrawn / abandoned Mitchell, GASoutheast Oct 2016
Potomac Solar, LLC
Solar
80.0 MWWithdrawn / abandoned Frederick, MDPJM Apr 20162021
Solar project 782, Box Elder County
Solar
80.0 MWWithdrawn / abandoned Box Elder, UTWest Aug 2016target 2018
Solar project 812, Box Elder County
Solar
80.0 MWWithdrawn / abandoned Box Elder, UTWest Oct 2016target 2019
Solar project IC-524, Marengo County
Solar
80.0 MWWithdrawn / abandoned Marengo, ALSoutheast Nov 2016
Solar project IC-470, Dale County
Solar
79.7 MWWithdrawn / abandoned Dale, ALSoutheast Jul 2016
Solar project IC-450, Dale County
Solar
79.7 MWWithdrawn / abandoned Dale, ALSoutheast Mar 2016
Solar project IC-479, Dallas County
Solar
79.2 MWWithdrawn / abandoned Dallas, ALSoutheast Aug 2016
Solar project IC-488, Elmore County
Solar
79.2 MWWithdrawn / abandoned Elmore, ALSoutheast Aug 2016
ZEP Valley Wind Farm
Onshore wind
79.1 MWWithdrawn / abandoned Tazewell, ILPJM Oct 2016target 2025
Solar project IC-468, Greene County
Solar
78.9 MWWithdrawn / abandoned Greene, ALSoutheast Jul 2016
Solar project IC-431, Escambia County
Solar
78.6 MWWithdrawn / abandoned Escambia, ALSoutheast Feb 2016
Solar project IC-475, Hancock County
Solar
78.6 MWWithdrawn / abandoned Hancock, MSSoutheast Jul 2016
Solar project IC-432, Decatur County
Solar
78.6 MWWithdrawn / abandoned Decatur, GASoutheast Feb 2016
Solar project IC-454, Hancock County
Solar
78.5 MWWithdrawn / abandoned Hancock, MSSoutheast May 2016
Solar project IC-463, Newton County
Solar
78.5 MWWithdrawn / abandoned Newton, MSSoutheast May 2016
Solar project IC-451, Clarke County
Solar
78.5 MWWithdrawn / abandoned Clarke, MSSoutheast Apr 2016
Solar project IC-429, Marengo County
Solar
78.5 MWWithdrawn / abandoned Marengo, ALSoutheast Jan 2016
Solar
Solar
78.4 MWWithdrawn / abandoned Franklin, MEISO-NE Jun 2016target 2018
Solar
Solar
78.4 MWWithdrawn / abandoned Cheshire, NHISO-NE Jun 2016target 2018
Solar project 738, Crook County
Solar
78.3 MWWithdrawn / abandoned Crook, ORWest Apr 2016target 2018
Coso Solar 1
Solar
78.2 MWWithdrawn / abandoned Inyo, CACAISO May 2016target 2018
Onshore wind project GEN-2016-016, Edwards County
Onshore wind
78.2 MWWithdrawn / abandoned Edwards, KSSPP Mar 20162023
Solar project IC-452, Dale County
Solar
78.0 MWWithdrawn / abandoned Dale, ALSoutheast Apr 2016
Onshore wind project AC2-003, Botetourt County
Onshore wind
78.0 MWWithdrawn / abandoned Botetourt, VAPJM Nov 2016target 2023
Onshore wind project GI-56, Sullivan County
Onshore wind
77.5 MWWithdrawn / abandoned Sullivan, MOSoutheast May 2016target 2018
Solar project IC-521, Washington County
Solar
76.0 MWWithdrawn / abandoned Washington, GASoutheast Oct 2016
Onshore wind project 807, Carbon County
Onshore wind ยท Elk Mountain Wind, LLC
75.9 MWWithdrawn / abandoned Carbon, WYWest Sep 2016target 2019
Solar project IC-480, Escambia County
Solar
75.0 MWWithdrawn / abandoned Escambia, ALSoutheast Aug 2016
Solar project 280, Jackson County
Solar
75.0 MWWithdrawn / abandoned Jackson, ALSoutheast Feb 2016
Solar project 768, Iron County
Solar
75.0 MWWithdrawn / abandoned Iron, UTWest Jul 2016target 2018
Solar project IC-559, Clay County
Solar
75.0 MWWithdrawn / abandoned Clay, GASoutheast Dec 2016
Solar project AB2-171, Southampton County
Solar
75.0 MWWithdrawn / abandoned Southampton, VAPJM Apr 2016target 2018
Solar project IC-474, Perry County
Solar
75.0 MWWithdrawn / abandoned Perry, ALSoutheast Jul 2016
Solar project IC-517, Lee County
Solar
75.0 MWWithdrawn / abandoned Lee, GASoutheast Oct 2016
Solar project 284, Carroll County
Solar
75.0 MWWithdrawn / abandoned Carroll, TNSoutheast Feb 2016
Burkburnett Solar
Solar ยท Sunchase Power
75.0 MWWithdrawn / abandoned ERCOT Nov 2016target 2018
Solar project 278, Henry County
Solar
75.0 MWWithdrawn / abandoned Henry, TNSoutheast Jan 2016
Solar project IC-486, Scott County
Solar
75.0 MWWithdrawn / abandoned Scott, MSSoutheast Aug 2016
Onshore wind project GEN-2016-140, Texas County
Onshore wind
75.0 MWWithdrawn / abandoned Texas, OKSPP Nov 20162020
Onshore wind project GEN-2016-136, Texas County
Onshore wind
75.0 MWWithdrawn / abandoned Texas, OKSPP Nov 20162020
Solar project Q244, Pinal County
Solar
75.0 MWWithdrawn / abandoned Pinal, AZWest Mar 2016target 2019
Onshore wind project CLPT G9, Laramie County
Onshore wind
75.0 MWWithdrawn / abandoned Laramie, WYWest Dec 2016target 2019
Solar project Q237, Navajo County
Solar
75.0 MWWithdrawn / abandoned Navajo, AZWest Mar 2016target 2021
Onshore wind project AC1-195, Hardin County
Onshore wind
75.0 MWWithdrawn / abandoned Hardin, OHPJM Oct 2016target 2018
Solar
Solar
75.0 MWWithdrawn / abandoned Washington, MEISO-NE Oct 2016target 2022
Solar project 5691, Scotland County
Solar ยท Friesian Holdings LLC
75.0 MWWithdrawn / abandoned Scotland, NCSoutheast Jun 2016target 2023
Steam Turbines
Other
75.0 MWWithdrawn / abandoned Franklin, MEISO-NE Apr 2016target 2018
Solar project 140, Alachua County
Solar ยท Masked
75.0 MWWithdrawn / abandoned Alachua, FLSoutheast May 2016target 2021
Solar project 147A, Alachua County
Solar ยท Masked
74.9 MWWithdrawn / abandoned Alachua, FLSoutheast May 2016target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)