| Project | Capacity | Status |
|---|---|---|
| Solar project IC-509, Mitchell County Solar |
80.0 MW | Withdrawn / abandoned |
| Potomac Solar, LLC Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 782, Box Elder County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 812, Box Elder County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-524, Marengo County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-470, Dale County Solar |
79.7 MW | Withdrawn / abandoned |
| Solar project IC-450, Dale County Solar |
79.7 MW | Withdrawn / abandoned |
| Solar project IC-479, Dallas County Solar |
79.2 MW | Withdrawn / abandoned |
| Solar project IC-488, Elmore County Solar |
79.2 MW | Withdrawn / abandoned |
| ZEP Valley Wind Farm Onshore wind |
79.1 MW | Withdrawn / abandoned |
| Solar project IC-468, Greene County Solar |
78.9 MW | Withdrawn / abandoned |
| Solar project IC-431, Escambia County Solar |
78.6 MW | Withdrawn / abandoned |
| Solar project IC-475, Hancock County Solar |
78.6 MW | Withdrawn / abandoned |
| Solar project IC-432, Decatur County Solar |
78.6 MW | Withdrawn / abandoned |
| Solar project IC-454, Hancock County Solar |
78.5 MW | Withdrawn / abandoned |
| Solar project IC-463, Newton County Solar |
78.5 MW | Withdrawn / abandoned |
| Solar project IC-451, Clarke County Solar |
78.5 MW | Withdrawn / abandoned |
| Solar project IC-429, Marengo County Solar |
78.5 MW | Withdrawn / abandoned |
| Solar Solar |
78.4 MW | Withdrawn / abandoned |
| Solar Solar |
78.4 MW | Withdrawn / abandoned |
| Solar project 738, Crook County Solar |
78.3 MW | Withdrawn / abandoned |
| Coso Solar 1 Solar |
78.2 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2016-016, Edwards County Onshore wind |
78.2 MW | Withdrawn / abandoned |
| Solar project IC-452, Dale County Solar |
78.0 MW | Withdrawn / abandoned |
| Onshore wind project AC2-003, Botetourt County Onshore wind |
78.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-56, Sullivan County Onshore wind |
77.5 MW | Withdrawn / abandoned |
| Solar project IC-521, Washington County Solar |
76.0 MW | Withdrawn / abandoned |
| Onshore wind project 807, Carbon County Onshore wind ยท Elk Mountain Wind, LLC |
75.9 MW | Withdrawn / abandoned |
| Solar project IC-480, Escambia County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 280, Jackson County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 768, Iron County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project IC-559, Clay County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project AB2-171, Southampton County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project IC-474, Perry County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project IC-517, Lee County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 284, Carroll County Solar |
75.0 MW | Withdrawn / abandoned |
| Burkburnett Solar Solar ยท Sunchase Power |
75.0 MW | Withdrawn / abandoned |
| Solar project 278, Henry County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project IC-486, Scott County Solar |
75.0 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2016-140, Texas County Onshore wind |
75.0 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2016-136, Texas County Onshore wind |
75.0 MW | Withdrawn / abandoned |
| Solar project Q244, Pinal County Solar |
75.0 MW | Withdrawn / abandoned |
| Onshore wind project CLPT G9, Laramie County Onshore wind |
75.0 MW | Withdrawn / abandoned |
| Solar project Q237, Navajo County Solar |
75.0 MW | Withdrawn / abandoned |
| Onshore wind project AC1-195, Hardin County Onshore wind |
75.0 MW | Withdrawn / abandoned |
| Solar Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 5691, Scotland County Solar ยท Friesian Holdings LLC |
75.0 MW | Withdrawn / abandoned |
| Steam Turbines Other |
75.0 MW | Withdrawn / abandoned |
| Solar project 140, Alachua County Solar ยท Masked |
75.0 MW | Withdrawn / abandoned |
| Solar project 147A, Alachua County Solar ยท Masked |
74.9 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)185 ยท 25.4 GW
- Southeast (non-ISO utilities)212 ยท 25.1 GW
- PJM (Mid-Atlantic, Midwest)250 ยท 23.8 GW
- West (non-ISO utilities)255 ยท 23.7 GW
- CAISO (California)96 ยท 19.6 GW
- SPP (Southwest Power Pool)110 ยท 19.5 GW
- ERCOT (Texas)39 ยท 7,318 MW
- ISO-NE (New England)22 ยท 4,400 MW
- NYISO (New York)25 ยท 2,046 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)