SOLAR Β· SOUTHEAST

Solar project IC-488, Elmore County

Solar project IC-488, Elmore County is a 79.2 MW solar request withdrawn in the Southeast interconnection queue, in Elmore County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2016 (completed)
  2. Withdrawn / abandonedMar 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-488
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Bouldin Dam - Forbes Road 115 kV Line
Location
Elmore County, Alabama
Technology
Solar: 79.2 MW
Total requested
79.2 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
31 August 2016
Withdrawn
March 2017

Location

Marker shows the centre of Elmore County; the queue data does not give exact sites.

Power plants in Alabama Β· Transmission lines in Alabama

Other requests in Elmore County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem