ONSHORE WIND Β· PJMOnshore wind project AC1-195, Hardin County
Onshore wind project AC1-195, Hardin County is a 75.0 MW onshore wind request withdrawn in the PJM interconnection queue, in Hardin County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2016 (completed)
- Withdrawn / abandonedMay 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AC1-195
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Dunkirk-Ada 69kV
- Location
- Hardin County, Ohio
- Technology
- Wind: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 October 2016
- Proposed online date
- December 2018
- Withdrawn
- May 2017
Location
Marker shows the centre of Hardin County; the queue data does not give exact sites.
Other requests in Hardin County
- Scioto SolarSolar + storage Β· 100 MW Β· agreement signed
- Scioty SolarSolar Β· 50.0 MW Β· agreement signed
- Scioto SolarSolar Β· 30.0 MW Β· agreement signed
- Strawhat Solar Energy CenterSolar Β· 110 MW Β· suspended
- Hardin Energy Center βΓΓ¬ Storage IIBattery storage Β· 55.0 MW Β· suspended
- Hardin Energy Center βΓΓ¬ Storage IBattery storage Β· 50.0 MW Β· suspended
- Scioto Ridge Wind FarmOnshore wind Β· 250 MW Β· built
- Hardin Energy Center βΓΓ¬ Phase 3Solar Β· 230 MW Β· built
- Hardin Energy Center βΓΓ¬ Phase 2Solar Β· 150 MW Β· built
- Hardin Energy CenterSolar Β· 130 MW Β· built
- Hog Creek Wind FarmOnshore wind Β· 48.3 MW Β· built
- Hardin Energy Center - Phase 3Solar Β· 20.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem