Solar project IC-559, Clay County

Solar project IC-559, Clay County is a 75.0 MW solar request withdrawn in the Southeast interconnection queue, in Clay County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2016 (completed)
  2. Withdrawn / abandonedAug 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-559
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Blakely Primary - George Dam 115 kV Line
Location
Clay County, Georgia
Technology
Solar: 75.0 MW
Total requested
75.0 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
12 December 2016
Withdrawn
August 2017

Location

Marker shows the centre of Clay County; the queue data does not give exact sites.