SOLAR Β· SOUTHEASTSolar project IC-326, Clay County
Solar project IC-326, Clay County is a 80.0 MW solar request withdrawn in the Southeast interconnection queue, in Clay County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2013 (completed)
- Withdrawn / abandonedOct 2018 (project stopped here)
- ConsentedMar 2015 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-326
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Blakely Primary - George Dam 115 kV Line
- Location
- Clay County, Georgia
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 18 November 2013
- Agreement signed
- 27 March 2015
- Withdrawn
- October 2018
Location
Marker shows the centre of Clay County; the queue data does not give exact sites.
Other requests in Clay County
- SR ClaySolar Β· 125 MW Β· built
- Solar project IC-458, Clay CountySolar Β· 122 MW Β· withdrawn
- Solar + storage project IC-836, Clay CountySolar + storage Β· 120 MW Β· withdrawn
- Other project IC-219, Clay CountyOther Β· 110 MW Β· withdrawn
- Solar project IC-559, Clay CountySolar Β· 75.0 MW Β· withdrawn
- Solar project IC-603, Clay CountySolar Β· 60.0 MW Β· withdrawn
- Solar project IC-353, Clay CountySolar Β· 20.0 MW Β· withdrawn
- Solar project IC-300, Clay CountySolar Β· 20.0 MW Β· withdrawn
- Solar project IC-289, Clay CountySolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem