πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

SOLAR Β· SOUTHEAST

SR Clay

SR Clay is a 125 MW solar request built and operating in the Southeast interconnection queue, in Clay County, Georgia, connecting to Georgia Transmission.

Queue statusOperating
  1. PlanningQueued Dec 2023 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingAug 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GI-105
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Georgia Transmission
Connection point (POI)
Huckleberry 115 kV Sub
Location
Clay County, Georgia
Technology
Solar: 125 MW
Total requested
125 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
31 December 2023
Came online
August 2022

Location

Marker shows the centre of Clay County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Clay County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem