United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2024 requests) โ page 11
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project C4-116, Owyhee County Battery storage |
175 MW | Withdrawn / abandoned |
| Solar + storage project J3821, Walker County Solar + storage |
175 MW | Withdrawn / abandoned |
| Solar + storage project J3510, Cross County Solar + storage |
175 MW | Withdrawn / abandoned |
| Onshore wind project J3239, Christian County Onshore wind |
175 MW | Withdrawn / abandoned |
| Battery storage project J3817, Allegan County Battery storage |
175 MW | Withdrawn / abandoned |
| Solar + storage project C4-115, Juab County Solar + storage |
175 MW | Withdrawn / abandoned |
| Solar project IC-1240, Putnam County Solar |
175 MW | Withdrawn / abandoned |
| Solar project 607, Lawrence County Solar |
175 MW | Withdrawn / abandoned |
| Battery storage project J3266, Sargent County Battery storage |
175 MW | Withdrawn / abandoned |
| Solar project 245, Williamsburg County Solar |
175 MW | Withdrawn / abandoned |
| Solar + storage project 2024-G3 Solar + storage |
170 MW | Withdrawn / abandoned |
| Onshore wind project J3281, Marquette County Onshore wind |
170 MW | Withdrawn / abandoned |
| Flynn Energy Storage Battery storage ยท the New York Power Authority |
170 MW | Withdrawn / abandoned |
| Solar + storage project J3458, Cross County Solar + storage |
170 MW | Withdrawn / abandoned |
| Port Jefferson Energy Storage Battery storage ยท Port Jefferson Energy Storage, LLC |
168 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
167 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
167 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
166 MW | Withdrawn / abandoned |
| Solar project 640, Haywood County Solar |
165 MW | Withdrawn / abandoned |
| Surplus; J1669 Other |
165 MW | Withdrawn / abandoned |
| Zenith BESS Battery storage ยท Zenith Power LLC |
165 MW | Withdrawn / abandoned |
| Solar Solar |
165 MW | Withdrawn / abandoned |
| South Loop Energy Center Battery storage ยท Concurrent Holdco LLC |
161 MW | Withdrawn / abandoned |
| NY Niagara Falls 5800 Niagara Falls Blvd Storage Battery storage ยท Bergholtz Creek LLC |
161 MW | Withdrawn / abandoned |
| Yellow Barn Solar Solar ยท Yellow Barn Solar, LLC |
160 MW | Withdrawn / abandoned |
| Solar + storage project J3775, Desha County Solar + storage |
160 MW | Withdrawn / abandoned |
| Solar + storage project C4-109, Albany County Solar + storage |
160 MW | Withdrawn / abandoned |
| Marble River Storage Battery storage ยท Emeren US, LLC |
160 MW | Withdrawn / abandoned |
| Solar project J3589, Lincoln County Solar |
160 MW | Withdrawn / abandoned |
| Solar project J3429, Pemiscot County Solar |
160 MW | Withdrawn / abandoned |
| Other project J3437, Ogemaw County Other |
160 MW | Withdrawn / abandoned |
| Other project Q556, Navajo County Other |
160 MW | Withdrawn / abandoned |
| SBMT Energy Center, LLC Battery storage ยท SBMT Energy Center, LLC |
160 MW | Withdrawn / abandoned |
| Solar + storage project J3812, Phillips County Solar + storage |
159 MW | Withdrawn / abandoned |
| Solar project 958349, Cumberland County Solar ยท Masked |
157 MW | Withdrawn / abandoned |
| Gas project 957101, Cherokee County Gas |
156 MW | Withdrawn / abandoned |
| Solar project J3624, Columbia County Solar |
155 MW | Withdrawn / abandoned |
| Solar project J3380, Cleveland County Solar |
155 MW | Withdrawn / abandoned |
| Solar project J3238, Evangeline Parish County Solar |
155 MW | Withdrawn / abandoned |
| Solar project J3741, Cleveland County Solar |
155 MW | Withdrawn / abandoned |
| Solar + storage project IC-1274, Mitchell County Solar + storage |
155 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
153 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
153 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
153 MW | Withdrawn / abandoned |
| Villarreal Solar SLF Solar ยท Orion US Land Holding Co LLC |
153 MW | Withdrawn / abandoned |
| Veco Ranch Solar SLF Solar ยท Orion US Land Holding Co LLC |
153 MW | Withdrawn / abandoned |
| Gail Mountain Solar Solar ยท Gail Mountain Solar, LLC |
152 MW | Withdrawn / abandoned |
| Gail Mountain Storage Battery storage ยท Gail Mountain Solar, LLC |
152 MW | Withdrawn / abandoned |
| Olsovksy Storage Battery storage ยท BT Sky Storage, LLC |
151 MW | Withdrawn / abandoned |
| Augite Storage Battery storage ยท BT Augite Storage, LLC |
151 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)411 ยท 78.5 GW
- NYISO (New York)294 ยท 63.3 GW
- West (non-ISO utilities)237 ยท 46.1 GW
- Southeast (non-ISO utilities)195 ยท 32.8 GW
- ISO-NE (New England)97 ยท 13.2 GW
- ERCOT (Texas)50 ยท 10.0 GW
- SPP (Southwest Power Pool)29 ยท 7,503 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)