๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2024 requests) โ€” page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,313251.4 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,313 requests ยท page 11 of 27
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project C4-116, Owyhee County
Battery storage
175 MWWithdrawn / abandoned Owyhee, IDWest May 2024target 2027
Solar + storage project J3821, Walker County
Solar + storage
175 MWWithdrawn / abandoned Walker, TXMISO Apr 2024target 2028
Solar + storage project J3510, Cross County
Solar + storage
175 MWWithdrawn / abandoned Cross, ARMISO Apr 2024target 2028
Onshore wind project J3239, Christian County
Onshore wind
175 MWWithdrawn / abandoned Christian, ILMISO Apr 2024target 2028
Battery storage project J3817, Allegan County
Battery storage
175 MWWithdrawn / abandoned Allegan, MIMISO Apr 2024target 2028
Solar + storage project C4-115, Juab County
Solar + storage
175 MWWithdrawn / abandoned Juab, UTWest May 2024target 2029
Solar project IC-1240, Putnam County
Solar
175 MWWithdrawn / abandoned Putnam, GASoutheast Jan 2024
Solar project 607, Lawrence County
Solar
175 MWWithdrawn / abandoned Lawrence, TNSoutheast Jan 2024
Battery storage project J3266, Sargent County
Battery storage
175 MWWithdrawn / abandoned Sargent, NDMISO Apr 2024target 2028
Solar project 245, Williamsburg County
Solar
175 MWWithdrawn / abandoned Williamsburg, SCSoutheast Feb 2024target 2028
Solar + storage project 2024-G3
Solar + storage
170 MWWithdrawn / abandoned West Sep 2024target 2028
Onshore wind project J3281, Marquette County
Onshore wind
170 MWWithdrawn / abandoned Marquette, MIMISO Apr 2024target 2027
Flynn Energy Storage
Battery storage ยท the New York Power Authority
170 MWWithdrawn / abandoned Suffolk, NYNYISO Oct 2024
Solar + storage project J3458, Cross County
Solar + storage
170 MWWithdrawn / abandoned Cross, ARMISO Apr 2024target 2028
Port Jefferson Energy Storage
Battery storage ยท Port Jefferson Energy Storage, LLC
168 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2024
Battery Storage
Battery storage
167 MWWithdrawn / abandoned New London, CTISO-NE Feb 2024target 2028
Battery Storage
Battery storage
167 MWWithdrawn / abandoned Hartford, CTISO-NE Apr 2024target 2028
Battery Storage
Battery storage
166 MWWithdrawn / abandoned Providence, RIISO-NE May 2024target 2028
Solar project 640, Haywood County
Solar
165 MWWithdrawn / abandoned Haywood, TNSoutheast Aug 2024
Surplus; J1669
Other
165 MWWithdrawn / abandoned Jefferson Davis Parish, LAMISO Apr 2024target 2026
Zenith BESS
Battery storage ยท Zenith Power LLC
165 MWWithdrawn / abandoned Onondaga, NYNYISO Sep 2024
Solar
Solar
165 MWWithdrawn / abandoned Somerset, MEISO-NE Jun 2024target 2028
South Loop Energy Center
Battery storage ยท Concurrent Holdco LLC
161 MWWithdrawn / abandoned ERCOT May 2024target 2028
NY Niagara Falls 5800 Niagara Falls Blvd Storage
Battery storage ยท Bergholtz Creek LLC
161 MWWithdrawn / abandoned Niagara, NYNYISO Sep 2024
Yellow Barn Solar
Solar ยท Yellow Barn Solar, LLC
160 MWWithdrawn / abandoned Tompkins, NYNYISO Sep 2024
Solar + storage project J3775, Desha County
Solar + storage
160 MWWithdrawn / abandoned Desha, ARMISO Apr 2024target 2028
Solar + storage project C4-109, Albany County
Solar + storage
160 MWWithdrawn / abandoned Albany, WYWest May 2024target 2026
Marble River Storage
Battery storage ยท Emeren US, LLC
160 MWWithdrawn / abandoned Clinton, NYNYISO Sep 2024
Solar project J3589, Lincoln County
Solar
160 MWWithdrawn / abandoned Lincoln, MSMISO Apr 2024target 2028
Solar project J3429, Pemiscot County
Solar
160 MWWithdrawn / abandoned Pemiscot, MOMISO Apr 2024target 2028
Other project J3437, Ogemaw County
Other
160 MWWithdrawn / abandoned Ogemaw, MIMISO May 2024target 2027
Other project Q556, Navajo County
Other
160 MWWithdrawn / abandoned Navajo, AZWest May 2024target 2028
SBMT Energy Center, LLC
Battery storage ยท SBMT Energy Center, LLC
160 MWWithdrawn / abandoned Kings, NYNYISO Sep 2024
Solar + storage project J3812, Phillips County
Solar + storage
159 MWWithdrawn / abandoned Phillips, ARMISO Apr 2024target 2028
Solar project 958349, Cumberland County
Solar ยท Masked
157 MWWithdrawn / abandoned Cumberland, NCSoutheast Jun 2024
Gas project 957101, Cherokee County
Gas
156 MWWithdrawn / abandoned Cherokee, SCSoutheast Jun 2024
Solar project J3624, Columbia County
Solar
155 MWWithdrawn / abandoned Columbia, ARMISO Apr 2024target 2028
Solar project J3380, Cleveland County
Solar
155 MWWithdrawn / abandoned Cleveland, ARMISO Apr 2024target 2028
Solar project J3238, Evangeline Parish County
Solar
155 MWWithdrawn / abandoned Evangeline Parish, LAMISO Apr 2024target 2028
Solar project J3741, Cleveland County
Solar
155 MWWithdrawn / abandoned Cleveland, ARMISO Apr 2024target 2028
Solar + storage project IC-1274, Mitchell County
Solar + storage
155 MWWithdrawn / abandoned Mitchell, GASoutheast Mar 2024
Battery Storage
Battery storage
153 MWWithdrawn / abandoned Worcester, MAISO-NE Apr 2024target 2027
Battery Storage
Battery storage
153 MWWithdrawn / abandoned Worcester, MAISO-NE Apr 2024target 2027
Battery Storage
Battery storage
153 MWWithdrawn / abandoned Middlesex, MAISO-NE Mar 2024target 2028
Villarreal Solar SLF
Solar ยท Orion US Land Holding Co LLC
153 MWWithdrawn / abandoned Webb, TXERCOT May 2024target 2028
Veco Ranch Solar SLF
Solar ยท Orion US Land Holding Co LLC
153 MWWithdrawn / abandoned Webb, TXERCOT Jul 2024target 2029
Gail Mountain Solar
Solar ยท Gail Mountain Solar, LLC
152 MWWithdrawn / abandoned ERCOT Jan 2024target 2026
Gail Mountain Storage
Battery storage ยท Gail Mountain Solar, LLC
152 MWWithdrawn / abandoned ERCOT Feb 2024target 2026
Olsovksy Storage
Battery storage ยท BT Sky Storage, LLC
151 MWWithdrawn / abandoned Hill, TXERCOT Jan 2024target 2026
Augite Storage
Battery storage ยท BT Augite Storage, LLC
151 MWWithdrawn / abandoned Starr, TXERCOT Feb 2024target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)