United States βΊ Grid βΊ Interconnection queues βΊ Wyoming
SOLAR + STORAGE Β· WESTSolar + storage project C4-109, Albany County
Solar + storage project C4-109, Albany County is a 160 MW solar + storage request withdrawn in the West interconnection queue, in Albany County, Wyoming, connecting to PacifiCorp.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- C4-109
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Fort Sanders substation
- Location
- Albany County, Wyoming
- Technology
- Solar: 160 MW Β· Battery
- Total requested
- 160 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 15 May 2024
- Proposed online date
- December 2026
Location
Marker shows the centre of Albany County; the queue data does not give exact sites.
Other requests in Albany County
- Solar + storage project T2-026, Albany CountySolar + storage Β· 160 MW Β· in study
- Onshore wind project 719, Albany CountyOnshore wind Β· 280 MW Β· suspended
- Onshore wind project 409, Albany CountyOnshore wind Β· 320 MW Β· built
- Onshore wind project 920, Albany CountyOnshore wind Β· 630 MW Β· withdrawn
- Onshore wind project 298, Albany CountyOnshore wind Β· 400 MW Β· withdrawn
- Onshore wind project 132, Albany CountyOnshore wind Β· 361 MW Β· withdrawn
- Onshore wind project 935, Albany CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project 934, Albany CountyOnshore wind Β· 300 MW Β· withdrawn
- Solar + storage project 936, Albany CountySolar + storage Β· 300 MW Β· withdrawn
- Solar + storage project 933, Albany CountySolar + storage Β· 300 MW Β· withdrawn
- Onshore wind project C1-53, Albany CountyOnshore wind Β· 190 MW Β· withdrawn
- Solar project 1107, Albany CountySolar Β· 160 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem