Completed queue projects in PJM (Mid-Atlantic, Midwest) — page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,19297.6 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,192 requests · page 11 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Ladysmith Unit 5
Other
20.0 MWOperating Caroline, VAPJM Apr 20082009
Legore Bridge Solar Center Facility
Solar
20.0 MWOperating Frederick, MDPJM Oct 20152025
North Allegheny WF
Onshore wind
20.0 MWOperating Cambria, PAPJM Oct 20052009
Justin Court Energy Storage
Battery storage
20.0 MWOperating Hunterdon, NJPJM Apr 20182024
Kimberly Clark
Other
20.0 MWOperating Delaware, PAPJM Apr 20082008
Kendall Energy Center
Gas
20.0 MWOperating Grundy, ILPJM Apr 20132017
Cottontail Solar 4 aka East Chilli Solar
Solar
20.0 MWOperating Northumberland, PAPJM Feb 20192024
Pondtown Solar 2
Solar
20.0 MWOperating Queen Anne's, MDPJM Feb 20162022
Elizabeth River GT1
Gas
20.0 MWOperating City Of Chesapeake, VAPJM Jul 20072008
Morgan's Corner Solar
Solar
20.0 MWOperating Pasquotank, NCPJM Apr 20122015
Ladysmith Unit 3
Other
20.0 MWOperating Caroline, VAPJM Apr 20082009
Mehoopany Plant
Gas
20.0 MWOperating Wyoming, PAPJM Aug 20112013
Cottontail Solar 5 aka Walker Solar
Solar
20.0 MWOperating Juniata, PAPJM Feb 20192023
Bluebird Solar
Solar
20.0 MWOperating Harrison, KYPJM Feb 20172025
Carvers Creek Solar
Solar
20.0 MWOperating Gloucester, VAPJM Sep 20182025
McHenry Energy Storage
Battery storage
20.0 MWOperating Mchenry, ILPJM Oct 20132015
Clinch River Power Plant
Gas
20.0 MWOperating Russell, VAPJM Feb 20132016
Beacon Power Flywheel Station
Battery storage
20.0 MWOperating Luzerne, PAPJM Apr 20102014
Alpha Battery Storage Facility
Battery storage
20.0 MWOperating Warren, NJPJM Mar 20152019
Kendall Energy Center
Gas
20.0 MWOperating Grundy, ILPJM Apr 20132017
Mendota Hills Wind Farm
Onshore wind
20.0 MWOperating Lee, ILPJM Apr 20162019
Kelso Gap WF
Onshore wind
20.0 MWOperating Garrett, MDPJM Jul 20032006
Dorchester County Solar 1 Project
Solar
20.0 MWOperating Anne Arundel, MDPJM Aug 20112021
Hecate Energy Cherrydale
Solar
20.0 MWOperating Northampton, VAPJM Dec 20132017
Oak Hall Project C
Solar
20.0 MWOperating VAPJM Feb 20102016
Lakewood Cogeneration Plant
Gas
20.0 MWOperating Ocean, NJPJM Oct 20122015
Altavista Solar
Solar
20.0 MWOperating Campbell, VAPJM Oct 20162020
Carroll County Energy LLC
Gas
20.0 MWOperating Carroll, OHPJM Jan 20172020
Ross County Solar
Solar
20.0 MWOperating Ross, OHPJM Sep 20172025
Maplewood Solar
Solar
20.0 MWOperating Pittsylvania, VAPJM May 20172022
Solar project AB2-024, New Kent County
Solar
20.0 MWOperating New Kent, VAPJM Feb 20162017
Stagecoach Solar
Solar
20.0 MWOperating Halifax, VAPJM Sep 20162021
Rochelle Plant
Gas
20.0 MWOperating Hamilton, OHPJM Apr 20122013
Lappans 34.5kV Project
Solar
20.0 MWOperating Washington, MDPJM Jan 20112012
Big Plain 2
Solar
20.0 MWOperating Madison, OHPJM Sep 20172023
Watlington Solar
Solar
20.0 MWOperating Halifax, VAPJM Aug 20192023
Big Level Wind Farm
Onshore wind
20.0 MWOperating Potter, PAPJM Oct 20152019
Ocean Peaking Power
Gas
20.0 MWOperating Ocean, NJPJM Oct 20122015
Penn Solar (Cottontail 6)
Solar
20.0 MWOperating Snyder, PAPJM Mar 20192024
Darbytown GT4
Gas
20.0 MWOperating Henrico, VAPJM Jul 20072008
Ocean Peaking Power (Lakewood CT1, CT2)
Gas
20.0 MWOperating Ocean, NJPJM Oct 20062007
Liberty
Gas
20.0 MWOperating Delaware, PAPJM Jan 20082008
South River
Gas
20.0 MWOperating Middlesex, NJPJM Sep 20072012
Darbytown GT1
Gas
20.0 MWOperating Henrico, VAPJM Jul 20072008
Oak Hall Project A
Solar
20.0 MWOperating VAPJM Feb 20102016
Darbytown GT3
Gas
20.0 MWOperating Henrico, VAPJM Jul 20072008
Philipsburg-Clarence 34.5 kV
Solar
20.0 MWOperating Clearfield, PAPJM Mar 20192023
Gavin 1
Coal
20.0 MWOperating Adams, OHPJM Jan 20062007
Battery storage project Z1-107, Will County
Battery storage
20.0 MWOperating Will, ILPJM Oct 20132015
Yellowbud Solar
Solar
20.0 MWOperating Ross, OHPJM Aug 20172022
Page 11 of 24

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)