SOLAR · PJM

Carvers Creek Solar

Carvers Creek Solar is a 20.0 MW solar request built and operating in the PJM interconnection queue, in Gloucester County, Virginia, connecting to Dominion.

Queue statusOperating
  1. PlanningQueued Sep 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AE1-190
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Harmony Village-Shackleford 115 kV
Location
Gloucester County, Virginia
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
28 September 2018
Proposed online date
November 2025
Came online
December 2025

Location

Marker shows the centre of Gloucester County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Gloucester County