United States › Grid › Interconnection queues › Virginia
SOLAR · PJMCarvers Creek Solar
Carvers Creek Solar is a 50.0 MW solar request built and operating in the PJM interconnection queue, in Gloucester County, Virginia, connecting to Dominion.
Request details
- Queue ID
- AD1-041
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Harmony Village-Shackleford 115 kV
- Location
- Gloucester County, Virginia
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 3 August 2017
- Agreement signed
- 29 September 2020
- Proposed online date
- June 2024
- Came online
- August 2024
Location
Marker shows the centre of Gloucester County; the queue data does not give exact sites.
Other requests in Gloucester County
- Battery storage project AI2-318, Gloucester CountyBattery storage · 12.8 MW · in study
- Carvers Creek SolarSolar · 80.0 MW · built
- Winterberry SolarSolar · 20.0 MW · built
- Carvers Creek SolarSolar · 20.0 MW · built
- Camellia SolarSolar · 19.9 MW · built
- Gloucester SolarSolar · 19.8 MW · built
- Middle Pennisula Gas to Energy Power PlantOther · 6.2 MW · built
- Solar + storage project AF1-201, Gloucester CountySolar + storage · 150 MW · withdrawn
- Solar project AG2-058, Gloucester CountySolar · 70.0 MW · withdrawn
- Carvers Creek LLCBattery storage · 40.0 MW · withdrawn
- Battery storage project AG1-102, Gloucester CountyBattery storage · 19.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem