United States › Grid › Interconnection queues › Pennsylvania
SOLAR · PJMCottontail Solar 4 aka East Chilli Solar
Cottontail Solar 4 aka East Chilli Solar is a 20.0 MW solar request built and operating in the PJM interconnection queue, in Northumberland County, Pennsylvania, connecting to PPL.
Request details
- Queue ID
- AE2-059
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- Derry Tap-Derry Bus 69 kV
- Location
- Northumberland County, Pennsylvania
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 7 February 2019
- Proposed online date
- May 2024
- Came online
- August 2024
Location
Marker shows the centre of Northumberland County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Northumberland County
- Shamrock Energy CenterSolar · 20.0 MW · agreement signed
- Boyles Run SolarSolar · 15.9 MW · agreement signed
- Boyles Run SolarSolar · 15.9 MW · agreement signed
- Norwegian SolarSolar · 19.8 MW · suspended
- Northumberland SolarSolar · 65.0 MW · built
- Pine Hurst AcresOther · 0.0 MW · built
- Coal project R26, Northumberland CountyCoal · 940 MW · withdrawn
- Solar project AG2-430, Northumberland CountySolar · 60.0 MW · withdrawn
- Solar project AE1-127, Northumberland CountySolar · 50.0 MW · withdrawn
- Battery storage project AG1-050, Northumberland CountyBattery storage · 20.0 MW · withdrawn
- Solar project AH1-407, Northumberland CountySolar · 20.0 MW · withdrawn
- Solar project AH1-406, Northumberland CountySolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem