SOLAR Β· PJM

Solar project AH1-407, Northumberland County

Solar project AH1-407, Northumberland County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Northumberland County, Pennsylvania, connecting to PPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-407
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PPL
Connection point (POI)
Exchange Tap 69 kV III
Location
Northumberland County, Pennsylvania
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
10 September 2021
Proposed online date
October 2024
Withdrawn
December 2024

Location

Marker shows the centre of Northumberland County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Northumberland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem