United States › Grid › Interconnection queues › Virginia
SOLAR · PJMStagecoach Solar
Stagecoach Solar is a 20.0 MW solar request built and operating in the PJM interconnection queue, in Halifax County, Virginia, connecting to Dominion.
Request details
- Queue ID
- AC1-080
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Perth-Hickory Grove 115kV
- Location
- Halifax County, Virginia
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 30 September 2016
- Agreement signed
- 10 October 2019
- Proposed online date
- December 2021
- Came online
- April 2021
Location
Marker shows the centre of Halifax County; the queue data does not give exact sites.
Other requests in Halifax County
- Randolph SolarSolar · 500 MW · agreement signed
- Clover Creek SolarSolar · 90.0 MW · agreement signed
- Staunton SolarSolar · 36.0 MW · agreement signed
- Battery storage project AG2-270, Halifax CountyBattery storage · 150 MW · in study
- Solar project AH2-349, Halifax CountySolar · 142 MW · in study
- Battery storage project AI2-041, Halifax CountyBattery storage · 75.0 MW · in study
- CEP Solar, LLCSolar · 69.0 MW · in study
- Solar + storage project AH2-151, Halifax CountySolar + storage · 35.0 MW · in study
- Solar project AG2-262, Halifax CountySolar · 11.0 MW · in study
- Solar + storage project AI1-106, Halifax CountySolar + storage · 9.9 MW · in study
- Piney Creek SolarSolar · 80.0 MW · built
- Foxhound SolarSolar · 64.2 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem