SOLAR Β· OPERATIONAL

Oak Cottage

Oak Cottage is a 4.87 MW solar farm in Wales, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • Wales
Project stageOperating
  1. PlanningJan 2014 (completed)
  2. ConsentedJun 2014 (completed)
  3. ConstructionJul 2015 (completed)
  4. OperatingAug 2015 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.87 MW
Status
Operational
Technology
Solar Β· PV
Operator
Anesco
Region
Wales
Country
Wales
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
SA62 4PR
Coordinates
51.8240, -4.8623

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Oak Cottage compares

452nd of 662largest solar farms in the UK register
49th of 75in Wales
0.09%of listed UK solar farms capacity
β‰ˆ 4.3 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.87 MW station would generate roughly 4.3 GWh of electricity in a year, similar to the annual use of about 1,580 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in Wales All run by Anesco

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
Anesco
Planning authority
Pembrokeshire
Planning reference
13/0916/PA
Application submitted
28 January 2014
Permission granted
13 June 2014
Construction started
1 July 2015
Began operating
21 August 2015
Capacity in planning record
4.9 MW
Address
Land South of Oak Cottage, Wiston, Haverfordwest, Pembrokeshire, SA62 4PR, Dyfed, SA62 4PR
REPD reference
1774

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.