Langton (FIT)
Langton (FIT) is a 4.35 MW solar farm in Wales, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- Wales
Key facts
- Installed capacity
- 4.35 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Lightsource BP
- Region
- Wales
- Country
- Wales
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- SA65 9RH
- Coordinates
- 51.9647, -4.9931
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Langton (FIT) compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.35 MW station would generate roughly 3.8 GWh of electricity in a year, similar to the annual use of about 1,410 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in Wales All run by Lightsource BPNearby generating sites
- Crundale Β· 43.7 MW solar farm16.9 km
- Oak Cottage Β· 4.87 MW solar farm18.0 km
- North Tenement Β· 5 MW solar farm20.9 km
- Castle Pill Farm 1 - A, C Β· 3.15 MW onshore wind farm26.8 km
- Dyffryn Brodyn Wind Farm (GB) Β· 5.4 MW onshore wind farm28.4 km
- Dragon LNG Β· 9.97 MW solar farm29.1 km
- Wear Point Wind Farm Β· 8.2 MW onshore wind farm29.2 km
- West Farm Β· 7.63 MW solar farm30.2 km
Also operated by Lightsource BP
Lightsource BP operates 129 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Langton Farm Solar park
- Developer / operator
- Lightsource Renewable Energy
- Planning authority
- Pembrokeshire
- Planning reference
- 12/1160/PA
- Application submitted
- 18 March 2013
- Permission granted
- 19 November 2013
- Construction started
- 28 October 2015
- Began operating
- 3 December 2015
- Capacity in planning record
- 4.4 MW
- Address
- Land west of Langton Farm, Dwrbach, Fishguard, Pembrokeshire, Dyfed
- REPD reference
- 1661
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source