North Tenement
North Tenement is a 5 MW solar farm in Wales, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- Wales
Key facts
- Installed capacity
- 5 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Lightsource BP
- Region
- Wales
- Country
- Wales
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- SA62 3NX
- Coordinates
- 51.7771, -4.9882
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How North Tenement compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in Wales All run by Lightsource BPNearby generating sites
- Castle Pill Farm 1 - A, C Β· 3.15 MW onshore wind farm6.0 km
- Crundale Β· 43.7 MW solar farm6.7 km
- Dragon LNG Β· 9.97 MW solar farm8.3 km
- Wear Point Wind Farm Β· 8.2 MW onshore wind farm8.4 km
- Oak Cottage Β· 4.87 MW solar farm10.1 km
- West Farm Β· 7.63 MW solar farm10.6 km
- Pembroke Β· 2,199 MW gas-fired power station12.8 km
- Hoplass Β· 10.3 MW solar farm12.9 km
Also operated by Lightsource BP
Lightsource BP operates 129 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Developer / operator
- North Tenement Solar Farm Limited
- Planning authority
- Pembrokeshire
- Planning reference
- 15/0443/PA
- Application submitted
- 22 July 2015
- Permission granted
- 18 May 2016
- Construction started
- 10 February 2017
- Began operating
- 28 March 2017
- Capacity in planning record
- 5 MW
- Address
- North Tenement, Dredgeman Hill, Haverfordwest, Dyfed, Pembrokeshire, SA61 1XL
- REPD reference
- 5523
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.