SOLAR Β· OPERATIONAL

South Creake

South Creake is a 26 MW solar farm in East of England, England, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • East of England
  • England

Key facts

Installed capacity
26 MW
Status
Operational
Technology
Solar Β· PV
Operator
Lightsource BP
Region
East of England
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
NR21 9LY
Coordinates
52.8894, 0.7556

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How South Creake compares

35th of 662largest solar farms in the UK register
12th of 76in East of England
0.46%of listed UK solar farms capacity
β‰ˆ 23 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 26 MW station would generate roughly 23 GWh of electricity in a year, similar to the annual use of about 8,440 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in East of England All run by Lightsource BP

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
South Creake Solar Farm
Developer / operator
Lightsource BP
Planning authority
King's Lynn and West Norfolk
Planning reference
13/00336/FM
Application submitted
5 March 2013
Permission granted
4 June 2013
Construction started
16 November 2015
Began operating
11 March 2016
Capacity in planning record
26 MW
Address
Leicester Square Farm Leicester Road South Creake Norfolk, Norfolk, NR21 9NX
REPD reference
1777

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.