South Creake
South Creake is a 26 MW solar farm in East of England, England, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- East of England
- England
Key facts
- Installed capacity
- 26 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Lightsource BP
- Region
- East of England
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- NR21 9LY
- Coordinates
- 52.8894, 0.7556
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How South Creake compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 26 MW station would generate roughly 23 GWh of electricity in a year, similar to the annual use of about 8,440 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in East of England All run by Lightsource BPNearby generating sites
- Chiplow Β· 8.2 MW onshore wind farm4.8 km
- Jacks Lane (GB) Β· 15 MW onshore wind farm5.1 km
- Egmere Β· 21 MW solar farm5.3 km
- Carland Cross PV Β· 10 MW solar farm12.6 km
- Snettisham Β· 2.69 MW solar farm14.9 km
- Lexham Β· 7.92 MW solar farm16.1 km
- QEH Β· 0.81 MW onshore wind farm25.4 km
- Burntstalk Farm Β· 11.5 MW solar farm25.5 km
Also operated by Lightsource BP
Lightsource BP operates 129 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- South Creake Solar Farm
- Developer / operator
- Lightsource BP
- Planning authority
- King's Lynn and West Norfolk
- Planning reference
- 13/00336/FM
- Application submitted
- 5 March 2013
- Permission granted
- 4 June 2013
- Construction started
- 16 November 2015
- Began operating
- 11 March 2016
- Capacity in planning record
- 26 MW
- Address
- Leicester Square Farm Leicester Road South Creake Norfolk, Norfolk, NR21 9NX
- REPD reference
- 1777
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.