Burntstalk Farm

Burntstalk Farm is a 11.5 MW solar farm in East of England, England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • East of England
  • England
Project stageOperating
  1. PlanningOct 2012 (completed)
  2. ConsentedDec 2012 (completed)
  3. Construction (completed)
  4. OperatingMar 2013 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
11.5 MW
Status
Operational
Technology
Solar Β· PV
Operator
Octopus Investments
Region
East of England
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
PE32 1JA
Coordinates
52.6732, 0.6271

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Burntstalk Farm compares

120th of 662largest solar farms in the UK register
26th of 76in East of England
0.20%of listed UK solar farms capacity
β‰ˆ 10 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 11.5 MW station would generate roughly 10 GWh of electricity in a year, similar to the annual use of about 3,740 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in East of England All run by Octopus Investments

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Burntstalk Solar Park
Developer / operator
Lightsource Renewable Energy
Planning authority
Breckland
Planning reference
3PL/2012/1036/F
Application submitted
8 October 2012
Permission granted
21 December 2012
Began operating
30 March 2013
Capacity in planning record
11.5 MW
Address
Low Road, Narford, Kings Lynn, Norfolk, Norfolk
REPD reference
1713

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026