WIND Β· OPERATIONAL

Pickenham

Pickenham is a 4 MW onshore wind farm in East of England, England, operated by Temporis Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • East of England
  • England
Project stageOperating
  1. PlanningSep 2009 (completed)
  2. ConsentedSep 2010 (completed)
  3. Construction (completed)
  4. OperatingApr 2014 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Temporis Capital
Region
East of England
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
PE37 8JX
Coordinates
52.6256, 0.7335

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Pickenham compares

433rd of 488largest wind farms in the UK register
38th of 48in East of England
0.01%of listed UK wind farms capacity
β‰ˆ 9.1 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 4 MW station would generate roughly 9.1 GWh of electricity in a year, similar to the annual use of about 3,370 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in East of England All run by Temporis Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
North Pickenham Airfield
Developer / operator
Bernard Matthews Green Energy
Planning authority
Breckland
Planning reference
3PL/2009/0881/F
Application submitted
22 September 2009
Permission granted
24 September 2010
Began operating
1 April 2014
Capacity in planning record
4 MW
Address
North Pickenham Road, Breckland, Norfolk
REPD reference
3828

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.