Tullymurdoch
Tullymurdoch is a 14.4 MW onshore wind farm in Scotland, operated by Temporis Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- Scotland
Key facts
- Installed capacity
- 14.4 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- Temporis Capital
- Region
- Scotland
- Country
- Scotland
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- PH11 8LH
- Coordinates
- 56.6549, -3.3134
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Tullymurdoch compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 14.4 MW station would generate roughly 33 GWh of electricity in a year, similar to the annual use of about 12,150 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in Scotland All run by Temporis CapitalNearby generating sites
- Drumderg Windfarm Β· 36.8 MW onshore wind farm6.2 km
- Pitlochry Power Station - A Β· 15 MW hydroelectric station26.6 km
- Pitlochry Compensation Generation - A Β· 0.06 MW small hydro scheme26.6 km
- Clunie Β· 61.2 MW hydroelectric station26.7 km
- Clunie Dam - A Β· 0.18 MW small hydro scheme26.7 km
- Griffin Wind Farm Β· 189 MW onshore wind farm27.0 km
- Errol Β· 13 MW solar farm31.2 km
- Auquhirie Land Β· 6.9 MW onshore wind farm34.4 km
Also operated by Temporis Capital
Temporis Capital operates 20 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Tullymurdoch Wind Farm
- Developer / operator
- Temporis Capital
- Planning authority
- Perth and Kinross
- Planning reference
- 12/01423/FLL
- Application submitted
- 13 August 2012
- Permission granted
- 3 September 2014
- Construction started
- 24 August 2017
- Began operating
- 23 January 2018
- Capacity in planning record
- 14.4 MW
- Address
- Alyth, Blairgowrie, Tayside, Tayside, PH10
- REPD reference
- 4599
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.