πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
WIND Β· OPERATIONAL

Eye

Eye is a 6.8 MW onshore wind farm in East of England, England, operated by Temporis Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • East of England
  • England

Key facts

Installed capacity
6.8 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Temporis Capital
Region
East of England
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
SG18 9TA
Coordinates
52.3304, 1.1266

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Eye compares

382nd of 488largest wind farms in the UK register
35th of 48in East of England
0.02%of listed UK wind farms capacity
β‰ˆ 15 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 6.8 MW station would generate roughly 15 GWh of electricity in a year, similar to the annual use of about 5,740 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in East of England All run by Temporis Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Planning Application Withdrawn
Site name in planning record
J.W. Baldwin Wind Farm
Developer / operator
Eye Wind Power Ltd
Planning authority
Mid Suffolk
Planning reference
0385/11
Capacity in planning record
6.8 MW
Address
South east of Eye Airfield, Suffolk, Suffolk
REPD reference
2774

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.