EPR Eye Ltd
EPR Eye Ltd is a 14.3 MW biomass power station in East of England, England, operated by EPR. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Bioenergy
- East of England
- England
Key facts
- Installed capacity
- 14.3 MW
- Status
- Operational
- Technology
- Bioenergy
- Operator
- EPR
- Region
- East of England
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- IP23 8BW
- Coordinates
- 52.3321, 1.1255
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How EPR Eye Ltd compares
Biomass power stations burn organic material such as wood pellets, energy crops or agricultural residues to raise steam for a turbine.
All biomass power stations Power stations in East of EnglandNearby power stations
- Eye Β· 6.8 MW onshore wind farm0.2 km
- Eye Β· 5 MW onshore wind farm0.5 km
- Chediston Hall Β· 12.4 MW solar farm23.8 km
- Hook Valley Solar Park Β· 15.3 MW solar farm24.1 km
- Brickkiln Lane Β· 4.99 MW solar farm25.9 km
- Halesworth Β· 10 MW onshore wind farm27.5 km
- EPR Thetford Ltd Β· 41.5 MW biomass power station30.1 km
- Avenue Farm Β· 7.65 MW solar farm32.7 km
Also operated by EPR
EPR operates 7 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Eye Biomass Plant
- Developer / operator
- South Western Power (NOVERA)
- Planning authority
- Mid Suffolk
- Began operating
- 1 July 1992
- Capacity in planning record
- 14.3 MW
- Address
- Eye Biomass Plant , Eye Airfield, Site A , Eye Suffolk, Suffolk
- REPD reference
- 82
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.