Breach Solar

Breach Solar is a 67.4 MW solar farm in East of England, England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • East of England
  • England

Key facts

Installed capacity
67.4 MW
Status
Operational
Technology
Solar Β· PV
Operator
Octopus Investments
Region
East of England
Country
England
Combined heat & power
No
Postcode
CB25 0DB
Coordinates
52.2919, 0.3492

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Breach Solar compares

6th of 662largest solar farms in the UK register
2nd of 76in East of England
1.2%of listed UK solar farms capacity
β‰ˆ 59 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 67.4 MW station would generate roughly 59 GWh of electricity in a year, similar to the annual use of about 21,880 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in East of England All run by Octopus Investments

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Breach Farm - Solar farm
Developer / operator
Octopus Renewables Infrastructure Trust
Planning authority
East Cambridgeshire
Planning reference
DC/21/0968/FUL
Application submitted
29 April 2021
Permission granted
10 December 2021
Began operating
1 December 2023
Capacity in planning record
49.9 MW
Address
Land South Of Breach Farm Ness Road Burwell Cambridge, Cambridgeshire, CB25 0DB
REPD reference
8479

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.