Chittering 2
Chittering 2 is a 6.3 MW solar farm in East of England, England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- East of England
- England
Key facts
- Installed capacity
- 6.3 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Octopus Investments
- Region
- East of England
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- CB25 9PH
- Coordinates
- 52.3152, 0.2177
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Chittering 2 compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 6.3 MW station would generate roughly 5.5 GWh of electricity in a year, similar to the annual use of about 2,040 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in East of England All run by Octopus InvestmentsNearby generating sites
- Chittering Β· 4.99 MW solar farm0.4 km
- Stowbridge Β· 24.3 MW solar farm1.5 km
- Willburton 2 (Mingay Farm) Β· 19.3 MW solar farm4.7 km
- Wilburton Β· 4.99 MW solar farm4.8 km
- Burwell Β· 69.9 MW solar farm6.4 km
- Goosehall Β· 43.2 MW solar farm6.8 km
- Breach Solar Β· 67.4 MW solar farm9.3 km
- EPR Ely Ltd Β· 38 MW biomass power station11.0 km
Also operated by Octopus Investments
Octopus Investments operates 134 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Planning Permission Granted
- Site name in planning record
- Chittering Solar Farm - extension 2
- Developer / operator
- Abbey Renewables (North Fen Solar Energy)
- Planning authority
- South Cambridgeshire
- Planning reference
- S/1331/14/FL
- Application submitted
- 9 June 2014
- Permission granted
- 16 June 2015
- Capacity in planning record
- 9.6 MW
- Address
- Land east and south of Radical Farm, Chittering Drove, Chittering, Cambridgeshire, CB25 9PH, Cambridgeshire
- REPD reference
- 1939
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.