Key facts
- Installed capacity
- 19.3 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Octopus Investments
- Region
- East of England
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- CB6 3PU
- Coordinates
- 52.3351, 0.1571
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Willburton 2 (Mingay Farm) compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 19.3 MW station would generate roughly 17 GWh of electricity in a year, similar to the annual use of about 6,270 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in East of England All run by Octopus InvestmentsNearby generating sites
- Wilburton Β· 4.99 MW solar farm1.3 km
- Stowbridge Β· 24.3 MW solar farm4.2 km
- Chittering 2 Β· 6.3 MW solar farm4.7 km
- Chittering Β· 4.99 MW solar farm4.7 km
- EPR Ely Ltd Β· 38 MW biomass power station7.2 km
- Burwell Β· 69.9 MW solar farm11.1 km
- Goosehall Β· 43.2 MW solar farm11.4 km
- Breach Solar Β· 67.4 MW solar farm13.9 km
Also operated by Octopus Investments
Octopus Investments operates 134 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Mingay Farm - extension
- Developer / operator
- Octopus Imvetments
- Planning authority
- East Cambridgeshire
- Planning reference
- 13/00499/ESF
- Application submitted
- 11 July 2013
- Permission granted
- 30 October 2013
- Began operating
- 31 March 2014
- Capacity in planning record
- 19.3 MW
- Address
- Solar Farm, S/O Mingay Farm, Twentypence Road, Wilburton, Ely, Cambridgeshire, CB6
- REPD reference
- 1502
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.