Sycamore is a 19 MW solar farm in South East England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South East
- England
Key facts
- Installed capacity
- 19 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Octopus Investments
- Region
- South East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- TN29 9SY
- Coordinates
- 50.9924, 0.8763
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Sycamore compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 19 MW station would generate roughly 17 GWh of electricity in a year, similar to the annual use of about 6,170 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South East All run by Octopus InvestmentsNearby generating sites
- Little Cheyne Court Β· 59.8 MW onshore wind farm4.9 km
- Place Farm Β· 6.79 MW solar farm8.8 km
- Dungeness B Β· 1,040 MW nuclear power station10.7 km
- Dungeness A Β· 450 MW nuclear power station10.7 km
- Sellindge Β· 11.2 MW solar farm14.1 km
- Oaklands Β· 6.85 MW solar farm20.1 km
- Lenham Β· 6.61 MW solar farm28.5 km
- Widehurst Β· 4.99 MW solar farm31.7 km
Also operated by Octopus Investments
Octopus Investments operates 134 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Sycamore Farm
- Developer / operator
- BNRG Renewables
- Planning authority
- Folkestone and Hythe
- Planning reference
- Y12/0918/SH
- Application submitted
- 8 October 2012
- Permission granted
- 17 January 2013
- Construction started
- 11 February 2014
- Began operating
- 30 May 2014
- Capacity in planning record
- 20 MW
- Address
- Millbank Lane Old Romney Kent TN29 9SY, Kent
- REPD reference
- 1775
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.