πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
SOLAR Β· OPERATIONAL

Anglesey

Anglesey is a 14.9 MW solar farm in Wales, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • Wales
Project stageOperating
  1. PlanningNov 2012 (completed)
  2. ConsentedFeb 2013 (completed)
  3. ConstructionSep 2013 (completed)
  4. OperatingJun 2014 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
14.9 MW
Status
Operational
Technology
Solar Β· PV
Operator
Anesco
Region
Wales
Country
Wales
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
LL63 5SZ
Coordinates
53.1787, -4.4148

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Anglesey compares

78th of 662largest solar farms in the UK register
4th of 75in Wales
0.26%of listed UK solar farms capacity
β‰ˆ 13 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 14.9 MW station would generate roughly 13 GWh of electricity in a year, similar to the annual use of about 4,840 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in Wales All run by Anesco

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Bodorgan Solar Farm
Developer / operator
Anesco
Planning authority
Isle of Anglesey
Planning reference
10C114A
Application submitted
15 November 2012
Permission granted
9 February 2013
Construction started
15 September 2013
Began operating
20 June 2014
Capacity in planning record
12.6 MW
Address
Tai Moelion farm near Aberffraw, Anglesey, Isle of Anglesey
REPD reference
2104

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.