Low Farm is a 49.9 MW solar farm in South East England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South East
- England
Key facts
- Installed capacity
- 49.9 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Anesco
- Region
- South East
- Country
- England
- Grid connection (DUKES)
- HV
- Combined heat & power
- No
- Postcode
- PE24 4JS
Location
No coordinates are published for this station.
How Low Farm compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 49.9 MW station would generate roughly 44 GWh of electricity in a year, similar to the annual use of about 16,190 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South East All run by AnescoAlso operated by Anesco
Anesco operates 136 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Under Construction
- Site name in planning record
- Low Farm Solar Farm
- Developer / operator
- Gresham House / Anesco Limited
- Planning authority
- East Lindsey
- Planning reference
- S/195/02340/20
- Application submitted
- 22 December 2020
- Permission granted
- 29 March 2021
- Construction started
- 28 March 2023
- Capacity in planning record
- 49.9 MW
- Address
- Low Farm, Lincolnshire, PE24 2LA
- REPD reference
- 8053
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.