Jordanston Solar Farm

Jordanston Solar Farm is a 4.63 MW solar farm in Wales, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • Wales
Project stageOperating
  1. PlanningJun 2012 (completed)
  2. ConsentedSep 2012 (completed)
  3. Construction (completed)
  4. OperatingMar 2013 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.63 MW
Status
Operational
Technology
Solar Β· PV
Operator
Anesco
Region
Wales
Country
Wales
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
SA70 8NQ
Coordinates
51.6754, -4.7959

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Jordanston Solar Farm compares

483rd of 662largest solar farms in the UK register
54th of 75in Wales
0.08%of listed UK solar farms capacity
β‰ˆ 4.1 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.63 MW station would generate roughly 4.1 GWh of electricity in a year, similar to the annual use of about 1,500 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in Wales All run by Anesco

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
AEE Renewables
Planning authority
Pembrokeshire
Planning reference
12/0252/PA
Application submitted
28 June 2012
Permission granted
26 September 2012
Began operating
28 March 2013
Capacity in planning record
5 MW
Address
St Florence, Tenby, Dyfed, Dyfed, SA70 8NQ
REPD reference
1388

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.