SOLAR Β· OPERATIONAL

Chapel Hill

Chapel Hill is a 10.1 MW solar farm in Wales, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • Wales
Project stageOperating
  1. PlanningMay 2014 (completed)
  2. ConsentedJul 2014 (completed)
  3. ConstructionJan 2015 (completed)
  4. OperatingMar 2015 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
10.1 MW
Status
Operational
Technology
Solar Β· PV
Operator
Greencoat Capital
Region
Wales
Country
Wales
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
SA71 5HY
Coordinates
51.6423, -4.9484

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Chapel Hill compares

141st of 662largest solar farms in the UK register
12th of 75in Wales
0.18%of listed UK solar farms capacity
β‰ˆ 8.8 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 10.1 MW station would generate roughly 8.8 GWh of electricity in a year, similar to the annual use of about 3,270 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in Wales All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
Wessex Solar Energy
Planning authority
Pembrokeshire
Planning reference
14/0148/PA
Application submitted
14 May 2014
Permission granted
29 July 2014
Construction started
1 January 2015
Began operating
27 March 2015
Capacity in planning record
8 MW
Address
Land east of Chapel Hill, Orielton, Pembroke, Dyfed, Dyfed, SA71 5HY
REPD reference
2326

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026